Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2014 |
Principal Product | Pharmaceutical Manufacturing and Development |
NAICS | 325412 - Pharmaceutical Preparation Manufacturing |
SIC | 2834 - Pharmaceutical Preparations |
Sales | $100,000,000-$500,000,000 |
# of Employees | 620 |
Plant Area (Sq.Ft.) | 505,000 |
Annual Production | 3,993 Bushels |
Production Hrs. Annual | 8,760 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,346,813 | 41,694,502 | kWh | $0.03 |
Electricity Demand | $1,360,410 | 89,972 | kW-months/year | $15.12 |
Natural Gas | $1,335,397 | 261,044 | MMBtu | $5.12 |
TOTAL ENERGY COSTS | $4,306,094 | |||
RECOMMENDED SAVINGS* | $841,066 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $430,541 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Administrative Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Administrative Changes | Ancillary Material Cost | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $235 Cost: - |
$138 | 4,660 | $97 | 6 | - | - | - | - | - | - | - | - | - | - | - | - |
$138 4,660 kWh |
$97 6 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.4115 RECOVER AND REUSE COOLING WATER |
Savings: $5,500 Cost: $2,000 |
- | - | - | - | - | - | - | - | $3,770 | 625 | - | - | - | - | $1,730 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$3,770 625 Tgal |
- - $ |
- - $ |
$1,730 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $10,400 Cost: $10,000 |
$(-100) | (-3,380) | $(-70) | (-5) | - | - | $10,570 | 2,064 | - | - | - | - | - | - | - | - |
$(-100) (-3,380) kWh |
$(-70) (-5) kW-months/year |
- - $ |
$10,570 2,064 MMBtu |
- - Tgal |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,016 Cost: $1,000 |
$2,539 | 86,000 | $1,777 | 118 | $(-300) | - | - | - | - | - | - | - | - | - | - | - |
$2,539 86,000 kWh |
$1,777 118 kW-months/year |
$(-300) - $ |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2492 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR |
Savings: $332,549 Cost: $400,000 |
$36,159 | 1,224,879 | $134,299 | 8,904 | - | - | $162,091 | 31,658 | - | - | - | - | - | - | - | - |
$36,159 1,224,879 kWh |
$134,299 8,904 kW-months/year |
- - $ |
$162,091 31,658 MMBtu |
- - Tgal |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $19,208 Cost: $40,430 |
$17,941 | 60,776 | $1,267 | 83 | - | - | - | - | - | - | - | - | - | - | - | - |
$17,941 60,776 kWh |
$1,267 83 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4113 INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS |
Savings: $11,334 Cost: $18,902 |
$6,667 | 225,859 | $4,667 | 310 | - | - | - | - | - | - | - | - | - | - | - | - |
$6,667 225,859 kWh |
$4,667 310 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2622 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL |
Savings: $377,548 Cost: $1,083,820 |
$109,567 | 3,711,630 | $267,981 | 17,767 | - | - | - | - | - | - | - | - | - | - | - | - |
$109,567 3,711,630 kWh |
$267,981 17,767 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $45,862 Cost: $9,000 |
$(-26) | (-865) | $(-1,012) | (-67) | - | - | - | - | - | - | - | - | $46,900 | - | - | - |
$(-26) (-865) kWh |
$(-1,012) (-67) kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
$46,900 - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.5217 REUSE / RECYCLE/ SELL PAPER PRODUCTS |
Savings: $22,280 Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | $22,280 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
$22,280 - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $8,744 Cost: $12,000 |
$(-45) | (-1,511) | - | - | - | - | - | - | - | - | - | - | $8,789 | - | - | - |
$(-45) (-1,511) kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
$8,789 - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $3,390 Cost: - |
- | - | - | - | - | - | - | - | - | - | $3,390 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
$3,390 - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $841,066 Cost: $1,577,152 |
$172,840 | 5,308,048 | $409,006 | 27,115 | $(-300) | - | $172,661 | 33,722 | $3,770 | 625 | $3,390 | - | $77,969 | - | $1,730 | - | $172,840 5,308,048 kWh |
$409,006 27,115 kW-months/year |
$(-300) - $ |
$172,661 33,722 MMBtu |
$3,770 625 Tgal |
$3,390 - $ |
$77,969 - $ |
$1,730 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $430,541 Cost: $1,124,722 |
$116,227 | 3,937,258 | $272,675 | 18,078 | - | - | $10,570 | 2,064 | - | - | - | - | $31,069 | - | - | - | $116,227 3,937,258 kWh |
$272,675 18,078 kW-months/year |
- - $ |
$10,570 2,064 MMBtu |
- - Tgal |
- - $ |
$31,069 - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Administrative Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Administrative Changes | Ancillary Material Cost | Water Consumption |