Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2015 |
Principal Product | Acoustic and Thermal Insulation |
NAICS | 327993 - Mineral Wool Manufacturing |
SIC | 3296 - Mineral Wool |
Sales | $10,000,000-$50,000,000 |
# of Employees | 170 |
Plant Area (Sq.Ft.) | 90,000 |
Annual Production | 6,436,451 Pieces |
Production Hrs. Annual | 5,500 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $687,185 | 10,344,600 | kWh | $0.07 |
Electricity Demand | $83,483 | 18,060 | kW-months/year | $4.62 |
Natural Gas | $7,928 | 1,002 | MMBtu | $7.91 |
TOTAL ENERGY COSTS | $786,593 | |||
RECOMMENDED SAVINGS* | $309,025 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,538 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2625 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE |
Savings: $860 Cost: - |
$780 | 12,264 | $80 | 17 | - | - | - | - |
$780 12,264 kWh |
$80 17 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $221,454 Cost: $15,345 |
$190,381 | 2,992,000 | $31,073 | 6,528 | - | - | - | - |
$190,381 2,992,000 kWh |
$31,073 6,528 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2211 USE OPTIMUM TEMPERATURE |
Savings: $46,665 Cost: - |
$46,665 | 733,381 | - | - | - | - | - | - |
$46,665 733,381 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $4,804 Cost: $34,000 |
$4,130 | 64,900 | $674 | 142 | - | - | - | - |
$4,130 64,900 kWh |
$674 142 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $3,759 Cost: $5,000 |
$2,834 | 44,531 | $925 | 194 | - | - | - | - |
$2,834 44,531 kWh |
$925 194 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,964 Cost: $1,000 |
$3,064 | 48,159 | $500 | 105 | $(-600) | - | - | - |
$3,064 48,159 kWh |
$500 105 kW-months/year |
$(-600) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $15,405 Cost: $66,200 |
$13,040 | 204,930 | $2,365 | 497 | - | - | - | - |
$13,040 204,930 kWh |
$2,365 497 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.642 INSTALL SENSORS TO DETECT AND AVOID JAMS |
Savings: $7,714 Cost: $120,000 |
- | - | - | - | $7,714 | - | - | - |
- - kWh |
- - kW-months/year |
$7,714 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $5,400 Cost: - |
- | - | - | - | - | - | $5,400 | - |
- - kWh |
- - kW-months/year |
- - $ |
$5,400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $309,025 Cost: $241,545 |
$260,894 | 4,100,165 | $35,617 | 7,483 | $7,114 | - | $5,400 | - | $260,894 4,100,165 kWh |
$35,617 7,483 kW-months/year |
$7,114 - $ |
$5,400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,538 Cost: $121,000 |
$3,844 | 60,423 | $580 | 122 | $7,114 | - | - | - | $3,844 60,423 kWh |
$580 122 kW-months/year |
$7,114 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost |