Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2024 |
Principal Product | Industrial fans |
NAICS | 333413 - Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
SIC | 3564 - Blowers And Fans |
Sales | $50,000,000-$100,000,000 |
# of Employees | 114 |
Plant Area (Sq.Ft.) | 87,000 |
Annual Production | 31,413 Units |
Production Hrs. Annual | 2,168 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $91,617 | 1,173,709 | kWh | $0.08 |
Electricity Demand | $35,930 | 5,157 | kW-months/year | $6.97 |
Electricity Fees | $4,748 | - | $ | - |
Natural Gas | $9,911 | 6,421 | MMBtu | $1.54 |
Other Gas | $2,574 | 1 | MMBtu | $2,574.00 |
TOTAL ENERGY COSTS | $147,294 | |||
RECOMMENDED SAVINGS* | $10,363 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $2,975 Cost: - |
$2,095 | 26,827 | $880 | 126 | - | - | - | - | - | - | - | - |
$2,095 26,827 kWh |
$880 126 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,335 Cost: $1,068 |
$894 | 11,441 | $441 | 64 | - | - | - | - | - | - | - | - |
$894 11,441 kWh |
$441 64 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $684 Cost: - |
$458 | 5,876 | $226 | 32 | - | - | - | - | - | - | - | - |
$458 5,876 kWh |
$226 32 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $452 Cost: $487 |
$319 | 4,081 | $133 | 19 | - | - | - | - | - | - | - | - |
$319 4,081 kWh |
$133 19 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $3,614 Cost: $6,258 |
- | - | $177 | 25 | $3,437 | - | - | - | - | - | - | - |
- - kWh |
$177 25 kW-months/year |
$3,437 - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $399 Cost: $1,254 |
$358 | 4,590 | - | - | - | - | - | - | $34 | - | $7 | - |
$358 4,590 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$34 - $ |
$7 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $303 Cost: $900 |
$203 | 2,601 | $100 | 14 | - | - | - | - | - | - | - | - |
$203 2,601 kWh |
$100 14 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $601 Cost: $2,093 |
- | - | - | - | - | - | $601 | 390 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$601 390 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $10,363 Cost: $12,060 |
$4,327 | 55,416 | $1,957 | 281 | $3,437 | - | $601 | 390 | $34 | - | $7 | - | $4,327 55,416 kWh |
$1,957 281 kW-months/year |
$3,437 - $ |
$601 390 MMBtu |
$34 - $ |
$7 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Ancillary Material Cost |