Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2025 |
Principal Product | Injection Molded and Extruded Plastic Components for Motor Vehicles |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3714 - Motor Vehicle Parts And Accessories |
Sales | $100,000,000-$500,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 125,000 |
Annual Production | 1,020,865 Units |
Production Hrs. Annual | 6,420 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $256,634 | 3,348,063 | kWh | $0.08 |
Electricity Demand | $42,979 | 8,595 | kW-months/year | $5.00 |
Electricity Fees | $5,654 | - | $ | - |
Natural Gas | $6,589 | 794 | MMBtu | $8.30 |
TOTAL ENERGY COSTS | $312,942 | |||
RECOMMENDED SAVINGS* | $33,190 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $5,147 Cost: $1,610 |
$4,574 | 59,637 | $573 | 115 | - | - | - | - | - | - |
$4,574 59,637 kWh |
$573 115 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $15,813 Cost: $5,000 |
$12,542 | 163,522 | $3,271 | 654 | - | - | - | - | - | - |
$12,542 163,522 kWh |
$3,271 654 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7313 RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING |
Savings: $6,529 Cost: $7,106 |
$4,552 | 59,354 | - | - | $1,977 | 238 | - | - | - | - |
$4,552 59,354 kWh |
- - kW-months/year |
$1,977 238 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT |
Savings: $2,612 Cost: $306 |
$2,612 | 34,058 | - | - | - | - | - | - | - | - |
$2,612 34,058 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $1,550 Cost: $1,184 |
$1,550 | 20,205 | - | - | - | - | - | - | - | - |
$1,550 20,205 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $715 Cost: $1,235 |
$635 | 8,276 | $80 | 16 | - | - | - | - | - | - |
$635 8,276 kWh |
$80 16 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $513 Cost: - |
$456 | 5,942 | $57 | 11 | - | - | - | - | - | - |
$456 5,942 kWh |
$57 11 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $311 Cost: $509 |
$235 | 3,058 | $25 | 5 | - | - | $39 | - | $12 | - |
$235 3,058 kWh |
$25 5 kW-months/year |
- - MMBtu |
$39 - $ |
$12 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $33,190 Cost: $16,950 |
$27,156 | 354,052 | $4,006 | 801 | $1,977 | 238 | $39 | - | $12 | - | $27,156 354,052 kWh |
$4,006 801 kW-months/year |
$1,977 238 MMBtu |
$39 - $ |
$12 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost |