Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Florida |
---|---|
Assessment Year | 1999 |
Principal Product | Plastic Bottles |
NAICS | n/a |
SIC | 3085 - Plastics Bottles |
Sales | $50,000,000-$100,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 193,000 |
Annual Production | 700,000,000 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $504,065 | 13,771,981 | kWh | $0.04 |
Electricity Demand | $220,830 | 28,277 | kW-months/year | $7.81 |
Electricity Fees | $105,348 | - | $ | - |
TOTAL ENERGY COSTS | $830,243 | |||
RECOMMENDED SAVINGS* | $514,247 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $59,329 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Increase in Production | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $192,386 Cost: $82,242 |
$313,544 | 7,126,905 | $74,570 | 789 | $(-195,728) | (-29,657) | - | - | - | - | - | - |
$313,544 7,126,905 kWh |
$74,570 789 kW-months/year |
$(-195,728) (-29,657) MMBtu |
- - lb |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $8,006 Cost: $60 |
$6,427 | 145,955 | $1,579 | 16 | - | - | - | - | - | - | - | - |
$6,427 145,955 kWh |
$1,579 16 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $5,521 Cost: $1,500 |
$5,521 | 125,440 | - | - | - | - | - | - | - | - | - | - |
$5,521 125,440 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,539 Cost: $834 |
$1,539 | 34,877 | - | - | - | - | - | - | - | - | - | - |
$1,539 34,877 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $3,215 Cost: - |
$1,078 | 24,619 | $2,137 | 16 | - | - | - | - | - | - | - | - |
$1,078 24,619 kWh |
$2,137 16 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.1163 USE PLASTIC PALLETS INSTEAD OF WOOD |
Savings: $25,200 Cost: $14,070 |
- | - | - | - | - | - | $25,200 | 105 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$25,200 105 lb |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $262,532 Cost: $850,000 |
- | - | - | - | - | - | - | - | $262,532 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$262,532 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.125 |
Savings: $15,848 Cost: $75,000 |
- | - | - | - | - | - | - | - | - | - | $15,848 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
$15,848 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $514,247 Cost: $1,023,706 |
$328,109 | 7,457,796 | $78,286 | 821 | $(-195,728) | (-29,657) | $25,200 | 105 | $262,532 | - | $15,848 | - | $328,109 7,457,796 kWh |
$78,286 821 kW-months/year |
$(-195,728) (-29,657) MMBtu |
$25,200 105 lb |
$262,532 - $ |
$15,848 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $59,329 Cost: $91,464 |
$14,565 | 330,891 | $3,716 | 32 | - | - | $25,200 | 105 | - | - | $15,848 | - | $14,565 330,891 kWh |
$3,716 32 kW-months/year |
- - MMBtu |
$25,200 105 lb |
- - $ |
$15,848 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Increase in Production | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Increase in Production |