Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Louisville |
---|---|
Assessment Year | 1996 |
Principal Product | Rotogravure Printing of Labels |
NAICS | n/a |
SIC | 2671 - Paper Coated & Laminated, Packaging |
Sales | $10,000,000-$50,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 45,000 |
Annual Production | 2,147,483,647 Pieces |
Production Hrs. Annual | 8,568 |
Location (State) | IN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $217,512 | 4,454,865 | kWh | $0.05 |
Electricity Demand | $24,086 | 9,614 | kW-months/year | $2.51 |
Natural Gas | $31,018 | 5,194 | MMBtu | $5.97 |
TOTAL ENERGY COSTS | $289,416 | |||
RECOMMENDED SAVINGS* | $58,042 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $37,160 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Administrative Changes | Ancillary Material Cost | By-product Production | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Administrative Changes | Ancillary Material Cost | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $14,936 Cost: $1,400 |
$14,936 | 312,134 | - | - | - | - | - | - | - | - | - | - | - | - |
$14,936 312,134 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $960 Cost: $40 |
$875 | 18,171 | $85 | 30 | - | - | - | - | - | - | - | - | - | - |
$875 18,171 kWh |
$85 30 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $4,464 Cost: $35 |
$4,112 | 85,873 | $352 | 140 | - | - | - | - | - | - | - | - | - | - |
$4,112 85,873 kWh |
$352 140 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $2,820 Cost: $7,774 |
- | - | $2,820 | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$2,820 - kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $459 Cost: $200 |
- | - | - | - | $459 | 33 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$459 33 MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $265 Cost: $265 |
- | - | - | - | - | - | - | - | - | - | - | - | $265 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
$265 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.8141 REGENERATE CLEANING SOLVENT ON-SITE AND REUSE |
Savings: $17,338 Cost: $3,000 |
- | - | - | - | - | - | - | - | $14,765 | - | $2,573 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$14,765 - $ |
$2,573 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.3131 USE EVAPORATION TO CONCENTRATE MATERIAL |
Savings: $16,800 Cost: $5,070 |
- | - | - | - | - | - | $16,800 | 9,240 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$16,800 9,240 gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $58,042 Cost: $17,784 |
$19,923 | 416,178 | $3,257 | 170 | $459 | 33 | $16,800 | 9,240 | $14,765 | - | $2,573 | - | $265 | - | $19,923 416,178 kWh |
$3,257 170 kW-months/year |
$459 33 MMBtu |
$16,800 9,240 gal |
$14,765 - $ |
$2,573 - $ |
$265 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $37,160 Cost: $6,545 |
$19,923 | 416,178 | $437 | 170 | - | - | $16,800 | 9,240 | - | - | - | - | - | - | $19,923 416,178 kWh |
$437 170 kW-months/year |
- - MMBtu |
$16,800 9,240 gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Administrative Changes | Ancillary Material Cost | By-product Production | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Administrative Changes | Ancillary Material Cost | By-product Production |