Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 1998 |
Principal Product | Wrappers |
NAICS | n/a |
SIC | 2653 - Corrugated And Solid Fiber Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 103 |
Plant Area (Sq.Ft.) | 105,000 |
Annual Production | 0 Units |
Production Hrs. Annual | 4,160 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $121,382 | 2,422,333 | kWh | $0.05 |
Electricity Demand | $80,478 | 6,588 | kW-months/year | $12.22 |
Electricity Fees | $33,785 | - | $ | - |
Natural Gas | $77,969 | 17,951 | MMBtu | $4.34 |
TOTAL ENERGY COSTS | $313,614 | |||
RECOMMENDED SAVINGS* | $28,803 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $5,378 Cost: $2,188 |
$5,184 | 94,959 | $194 | 120 | - | - | - | - | - | - |
$5,184 94,959 kWh |
$194 120 kW-months/year |
- - MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,806 Cost: $500 |
$1,551 | 37,222 | $1,255 | 108 | - | - | - | - | - | - |
$1,551 37,222 kWh |
$1,255 108 kW-months/year |
- - MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $6,709 Cost: $6,300 |
- | - | - | - | $6,709 | 1,630 | - | - | - | - |
- - kWh |
- - kW-months/year |
$6,709 1,630 MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $3,138 Cost: $4,120 |
- | - | - | - | $3,138 | 1,712 | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,138 1,712 MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.3122 USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS |
Savings: $812 Cost: $800 |
- | - | - | - | - | - | - | - | $812 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$812 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4155 METER WASTE WATER |
Savings: $599 Cost: $900 |
- | - | - | - | - | - | - | - | $599 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$599 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $5,200 Cost: $100 |
- | - | - | - | - | - | $5,200 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$5,200 - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $4,161 Cost: $200 |
- | - | - | - | - | - | $4,161 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$4,161 - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $28,803 Cost: $15,108 |
$6,735 | 132,181 | $1,449 | 228 | $9,847 | 3,342 | $9,361 | - | $1,411 | - | $6,735 132,181 kWh |
$1,449 228 kW-months/year |
$9,847 3,342 MMBtu |
$9,361 - $ |
$1,411 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Water Consumption |