IAC logo
IAC Assessment: UM0130
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UM0130
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Michigan
Assessment Year 1999
Principal Product Graphite
NAICS n/a
SIC 3295 - Minerals, Ground Or Treated
Sales $5,000,000-$10,000,000
# of Employees 40
Plant Area (Sq.Ft.) 60,000
Annual Production 15,000,000 Pounds
Production Hrs. Annual 2,080
Location (State) MI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $79,393 815,651 kWh $0.10
Electricity Fees $3,972 - $ -
Natural Gas $15,285 2,717 MMBtu $5.63
TOTAL ENERGY COSTS $98,650
RECOMMENDED SAVINGS* $85,159 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $13,790
#|Description Savings
Cost
Status Electricity Usage Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Electricity Usage Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes
$ kWh $ MMBtu $ Tgal $ lb $ $
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$662
Cost:
-
$662 17,878 - - - - - - - - $662
17,878
kWh
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
02: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA Savings:
$1,970
Cost:
-
- - $1,970 350 - - - - - - -
-
kWh
$1,970
350
MMBtu
-
-
Tgal
-
-
lb
-
-
$
03: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION Savings:
$1,200
Cost:
$3,500
- - - - $1,200 937,500 - - - - -
-
kWh
-
-
MMBtu
$1,200
937,500
Tgal
-
-
lb
-
-
$
04: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$11,820
Cost:
-
- - - - - - $11,820 - - - -
-
kWh
-
-
MMBtu
-
-
Tgal
$11,820
-
lb
-
-
$
05: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER Savings:
$3,807
Cost:
-
- - $3,807 - - - - - - - -
-
kWh
$3,807
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
06: 4.5110 EXPAND OPERATIONS INTO UNUSED SPACE Savings:
$65,700
Cost:
$123,450
- - - - - - - - $65,700 - -
-
kWh
-
-
MMBtu
-
-
Tgal
-
-
lb
$65,700
-
$
TOTAL RECOMMENDED Savings:
$85,159
Cost:
$126,950
$662 17,878 $5,777 350 $1,200 937,500 $11,820 - $65,700 - $662
17,878
kWh
$5,777
350
MMBtu
$1,200
937,500
Tgal
$11,820
-
lb
$65,700
-
$
TOTAL IMPLEMENTED Savings:
$13,790
Cost:
-
- - $1,970 350 - - $11,820 - - - -
-
kWh
$1,970
350
MMBtu
-
-
Tgal
$11,820
-
lb
-
-
$
Savings
Cost
$ kWh $ MMBtu $ Tgal $ lb $ $
Electricity Usage Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Electricity Usage Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes