Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 1999 |
Principal Product | Plastic Orthopedic Implants and Injection Molded Parts |
NAICS | n/a |
SIC | 2821 - Plastics Materials And Resins |
Sales | $1,000,000-$5,000,000 |
# of Employees | 56 |
Plant Area (Sq.Ft.) | 18,000 |
Annual Production | 7,500 Pounds |
Production Hrs. Annual | 2,168 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $60,814 | 611,372 | kWh | $0.10 |
Electricity Fees | $(-1,410) | - | $ | - |
Natural Gas | $1,022 | 160 | MMBtu | $6.39 |
TOTAL ENERGY COSTS | $60,426 | |||
RECOMMENDED SAVINGS* | $204,502 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,107 |
#|Description |
Savings Cost |
Status | Electricity Usage | Solid Waste (non-haz) | Primary Product | Electricity Usage | Solid Waste (non-haz) | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $336 Cost: $300 |
$336 | 3,517 | - | - | - | - |
$336 3,517 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $461 Cost: - |
$461 | 4,689 | - | - | - | - |
$461 4,689 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $198 Cost: $500 |
$198 | 2,052 | - | - | - | - |
$198 2,052 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS |
Savings: $1,836 Cost: $200 |
- | - | $1,836 | 24,126 | - | - |
- - kWh |
$1,836 24,126 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $762 Cost: $200 |
- | - | $762 | 31,050 | - | - |
- - kWh |
$762 31,050 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.425 ELIMINATE/REDUCE REDUNDANT INSPECTIONS |
Savings: $5,909 Cost: $3,434 |
- | - | - | - | $5,909 | - |
- - kWh |
- - lb |
$5,909 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $195,000 Cost: $10,000 |
- | - | - | - | $195,000 | - |
- - kWh |
- - lb |
$195,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $204,502 Cost: $14,634 |
$995 | 10,258 | $2,598 | 55,176 | $200,909 | - | $995 10,258 kWh |
$2,598 55,176 lb |
$200,909 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,107 Cost: $3,934 |
$198 | 2,052 | - | - | $5,909 | - | $198 2,052 kWh |
- - lb |
$5,909 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Solid Waste (non-haz) | Primary Product | Electricity Usage | Solid Waste (non-haz) | Primary Product |