IAC logo
IAC Assessment: UM0166
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UM0166
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Michigan
Assessment Year 2000
Principal Product Fabricated Sheet Metal
NAICS n/a
SIC 3499 - Fabricated Metal Products, Nec
Sales $5,000,000-$10,000,000
# of Employees 75
Plant Area (Sq.Ft.) 45,522
Annual Production 13,000 Units
Production Hrs. Annual 4,160
Location (State) MI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $68,812 1,841,735 kWh $0.04
Electricity Demand $39,335 4,332 kW-months/year $9.08
Electricity Fees $(-584) - $ -
Natural Gas $16,268 3,563 MMBtu $4.57
TOTAL ENERGY COSTS $123,831
RECOMMENDED SAVINGS* $12,604 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $5,705
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$244
Cost:
$400
$244 8,206 - - $244
8,206
kWh
-
-
MMBtu
02: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$1,683
Cost:
$1,700
$1,683 45,135 - - $1,683
45,135
kWh
-
-
MMBtu
03: 2.7231 USE RADIANT HEATER FOR SPOT HEATING Savings:
$2,815
Cost:
$10,000
- - $2,815 616 -
-
kWh
$2,815
616
MMBtu
04: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS Savings:
$1,595
Cost:
$11,900
- - $1,595 544 -
-
kWh
$1,595
544
MMBtu
05: 2.2492 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR Savings:
$562
Cost:
$3,120
- - $562 123 -
-
kWh
$562
123
MMBtu
06: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$5,705
Cost:
$5,925
- - $5,705 1,355 -
-
kWh
$5,705
1,355
MMBtu
TOTAL RECOMMENDED Savings:
$12,604
Cost:
$33,045
$1,927 53,341 $10,677 2,638 $1,927
53,341
kWh
$10,677
2,638
MMBtu
TOTAL IMPLEMENTED Savings:
$5,705
Cost:
$5,925
- - $5,705 1,355 -
-
kWh
$5,705
1,355
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas