IAC Assessment: UM0171
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UM0171
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Michigan
Assessment Year 2000
Principal Product Steel processing
NAICS n/a
SIC 3312 - Blast Furnaces And Steel Mills
Sales $10,000,000-$50,000,000
# of Employees 80
Plant Area (Sq.Ft.) 296,050
Annual Production 850,000 Tons
Production Hrs. Annual 8,736
Location (State) MI
Source Yearly Cost Usage Unit Unit Cost
Electricity Demand $82,510 10,285 kW-months/year $8.02
Electricity Fees $7,215 - $ -
Natural Gas $512,682 149,269 MMBtu $3.43
TOTAL ENERGY COSTS $1,041,925
RECOMMENDED SAVINGS* $385,335 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $187,954
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (haz) Primary Product Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (haz) Primary Product
$ kWh $ kW-months/year $ MMBtu $ Tgal $ gal $ $
01: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$717
Cost:
$3,440
$717 24,326 - - - - - - - - - - $717
24,326
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
$
02: 2.2693 USE WASTE HEAT STEAM FOR ABSORPTION REFRIGERATION Savings:
$15,476
Cost:
$30,000
$8,722 316,237 $6,754 474 - - - - - - - - $8,722
316,237
kWh
$6,754
474
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
$
03: 2.1241 REDUCE EXCESSIVE BOILER BLOWDOWN Savings:
$2,065
Cost:
$4,430
- - - - $2,065 590 - - - - - - -
-
kWh
-
-
kW-months/year
$2,065
590
MMBtu
-
-
Tgal
-
-
gal
-
-
$
04: 3.3133 USE OTHER WASTE CONCENTRATION METHODS Savings:
$147,018
Cost:
$250,000
- - - - - - - - $147,018 2,038,400 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$147,018
2,038,400
gal
-
-
$
05: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION Savings:
$32,105
Cost:
$3,600
- - - - - - $32,105 11,889,460 - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$32,105
11,889,460
Tgal
-
-
gal
-
-
$
06: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$187,954
Cost:
$165,000
- - - - - - - - - - $187,954 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
$187,954
-
$
TOTAL RECOMMENDED Savings:
$385,335
Cost:
$456,470
$9,439 340,563 $6,754 474 $2,065 590 $32,105 11,889,460 $147,018 2,038,400 $187,954 - $9,439
340,563
kWh
$6,754
474
kW-months/year
$2,065
590
MMBtu
$32,105
11,889,460
Tgal
$147,018
2,038,400
gal
$187,954
-
$
TOTAL IMPLEMENTED Savings:
$187,954
Cost:
$165,000
- - - - - - - - - - $187,954 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
$187,954
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ gal $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (haz) Primary Product Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (haz) Primary Product