Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 2000 |
Principal Product | Steel processing |
NAICS | n/a |
SIC | 3312 - Blast Furnaces And Steel Mills |
Sales | $10,000,000-$50,000,000 |
# of Employees | 80 |
Plant Area (Sq.Ft.) | 296,050 |
Annual Production | 850,000 Tons |
Production Hrs. Annual | 8,736 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Demand | $82,510 | 10,285 | kW-months/year | $8.02 |
Electricity Fees | $7,215 | - | $ | - |
Natural Gas | $512,682 | 149,269 | MMBtu | $3.43 |
TOTAL ENERGY COSTS | $1,041,925 | |||
RECOMMENDED SAVINGS* | $385,335 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $187,954 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $717 Cost: $3,440 |
$717 | 24,326 | - | - | - | - | - | - | - | - | - | - |
$717 24,326 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2693 USE WASTE HEAT STEAM FOR ABSORPTION REFRIGERATION |
Savings: $15,476 Cost: $30,000 |
$8,722 | 316,237 | $6,754 | 474 | - | - | - | - | - | - | - | - |
$8,722 316,237 kWh |
$6,754 474 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1241 REDUCE EXCESSIVE BOILER BLOWDOWN |
Savings: $2,065 Cost: $4,430 |
- | - | - | - | $2,065 | 590 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,065 590 MMBtu |
- - Tgal |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.3133 USE OTHER WASTE CONCENTRATION METHODS |
Savings: $147,018 Cost: $250,000 |
- | - | - | - | - | - | - | - | $147,018 | 2,038,400 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$147,018 2,038,400 gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION |
Savings: $32,105 Cost: $3,600 |
- | - | - | - | - | - | $32,105 | 11,889,460 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$32,105 11,889,460 Tgal |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $187,954 Cost: $165,000 |
- | - | - | - | - | - | - | - | - | - | $187,954 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
$187,954 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $385,335 Cost: $456,470 |
$9,439 | 340,563 | $6,754 | 474 | $2,065 | 590 | $32,105 | 11,889,460 | $147,018 | 2,038,400 | $187,954 | - | $9,439 340,563 kWh |
$6,754 474 kW-months/year |
$2,065 590 MMBtu |
$32,105 11,889,460 Tgal |
$147,018 2,038,400 gal |
$187,954 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $187,954 Cost: $165,000 |
- | - | - | - | - | - | - | - | - | - | $187,954 | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
$187,954 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Primary Product |