Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 2001 |
Principal Product | Aluminum Castings |
NAICS | n/a |
SIC | 3365 - Aluminum Foundries |
Sales | $5,000,000-$10,000,000 |
# of Employees | 46 |
Plant Area (Sq.Ft.) | 55,000 |
Annual Production | 480 Tons |
Production Hrs. Annual | 2,040 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $69,535 | 1,292,497 | kWh | $0.05 |
Electricity Demand | $36,501 | 3,864 | kW-months/year | $9.45 |
Electricity Fees | $(-824) | - | $ | - |
Natural Gas | $132,092 | 28,959 | MMBtu | $4.56 |
TOTAL ENERGY COSTS | $237,304 | |||
RECOMMENDED SAVINGS* | $20,087 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,150 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,864 Cost: $450 |
$1,301 | 29,601 | $1,563 | 209 | - | - |
$1,301 29,601 kWh |
$1,563 209 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $994 Cost: $1,250 |
$635 | 21,395 | $359 | 48 | - | - |
$635 21,395 kWh |
$359 48 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $4,406 Cost: $2,264 |
- | - | - | - | $4,406 | 789 |
- - kWh |
- - kW-months/year |
$4,406 789 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $3,048 Cost: $6,185 |
- | - | - | - | $3,048 | 669 |
- - kWh |
- - kW-months/year |
$3,048 669 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $7,489 Cost: $1,400 |
- | - | - | - | $7,489 | 1,665 |
- - kWh |
- - kW-months/year |
$7,489 1,665 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $1,286 Cost: $500 |
- | - | - | - | $1,286 | 282 |
- - kWh |
- - kW-months/year |
$1,286 282 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $20,087 Cost: $12,049 |
$1,936 | 50,996 | $1,922 | 257 | $16,229 | 3,405 | $1,936 50,996 kWh |
$1,922 257 kW-months/year |
$16,229 3,405 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,150 Cost: $950 |
$1,301 | 29,601 | $1,563 | 209 | $1,286 | 282 | $1,301 29,601 kWh |
$1,563 209 kW-months/year |
$1,286 282 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |