IAC Assessment: UM0206
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UM0206
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Michigan
Assessment Year 2002
Principal Product Organic Chemicals
NAICS n/a
SIC 2869 - Industrial Organic Chemicals, Nec
Sales $100,000,000-$500,000,000
# of Employees 210
Plant Area (Sq.Ft.) 140,000
Annual Production 120,000,000 Pounds
Production Hrs. Annual 8,760
Location (State) MI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $441,178 19,529,920 kWh $0.02
Electricity Demand $532,669 2,562 kW-months/year $207.91
Electricity Fees $63,151 - $ -
Natural Gas $2,070,352 897,124 MMBtu $2.31
TOTAL ENERGY COSTS $3,415,600
RECOMMENDED SAVINGS* $189,258 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Water Disposal Other Liquid (non-haz) Increase in Production Electricity Usage Electricity Demand Water Disposal Other Liquid (non-haz) Increase in Production
$ kWh $ kW-months/year $ Tgal $ gal $ %
01: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$100,000
Cost:
$5,000
- - - - - - - - $100,000 - -
-
kWh
-
-
kW-months/year
-
-
Tgal
-
-
gal
$100,000
-
%
02: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE Savings:
$39,500
Cost:
$121,500
- - - - - - $39,500 64,281 - - -
-
kWh
-
-
kW-months/year
-
-
Tgal
$39,500
64,281
gal
-
-
%
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$35,341
Cost:
$105,000
$20,376 902,000 $14,965 864 - - - - - - $20,376
902,000
kWh
$14,965
864
kW-months/year
-
-
Tgal
-
-
gal
-
-
%
04: 3.4131 MINIMIZE CONTAMINATION OF WATER BEFORE TREATMENT Savings:
$10,650
Cost:
$26,000
- - - - $10,650 1,801,000 - - - - -
-
kWh
-
-
kW-months/year
$10,650
1,801,000
Tgal
-
-
gal
-
-
%
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,767
Cost:
$525
$1,530 61,457 $2,237 157 - - - - - - $1,530
61,457
kWh
$2,237
157
kW-months/year
-
-
Tgal
-
-
gal
-
-
%
TOTAL RECOMMENDED Savings:
$189,258
Cost:
$258,025
$21,906 963,457 $17,202 1,021 $10,650 1,801,000 $39,500 64,281 $100,000 - $21,906
963,457
kWh
$17,202
1,021
kW-months/year
$10,650
1,801,000
Tgal
$39,500
64,281
gal
$100,000
-
%
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
Tgal
-
-
gal
-
-
%
Savings
Cost
$ kWh $ kW-months/year $ Tgal $ gal $ %
Electricity Usage Electricity Demand Water Disposal Other Liquid (non-haz) Increase in Production Electricity Usage Electricity Demand Water Disposal Other Liquid (non-haz) Increase in Production