Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Utah |
---|---|
Assessment Year | 2003 |
Principal Product | rocket motor casings |
NAICS | 332313 - Plate Work Manufacturing |
SIC | 3443 - Fabricated Plate Work (boiler Shops) |
Sales | $10,000,000-$50,000,000 |
# of Employees | 40 |
Plant Area (Sq.Ft.) | 77,000 |
Annual Production | 100 Pieces |
Production Hrs. Annual | 4,160 |
Location (State) | UT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $49,221 | 2,313,137 | kWh | $0.02 |
Electricity Demand | $23,351 | 3,879 | kW-months/year | $6.02 |
Electricity Fees | $4,223 | - | $ | - |
Natural Gas | $79,705 | 28,088 | MMBtu | $2.84 |
TOTAL ENERGY COSTS | $156,500 | |||
RECOMMENDED SAVINGS* | $32,157 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $18,557 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $10,212 Cost: $710 |
$7,372 | 313,700 | $2,840 | 430 | - | - |
$7,372 313,700 kWh |
$2,840 430 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $3,536 Cost: $4,800 |
$2,460 | 105,400 | $1,076 | 163 | - | - |
$2,460 105,400 kWh |
$1,076 163 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $8,044 Cost: $9,000 |
$5,798 | 248,300 | $2,246 | 340 | - | - |
$5,798 248,300 kWh |
$2,246 340 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $1,693 Cost: - |
$932 | 39,900 | $761 | 115 | - | - |
$932 39,900 kWh |
$761 115 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1122 RE-SIZE CHARGING OPENINGS OR ADD A MOVABLE DOOR ON EQUIPMENT |
Savings: $3,430 Cost: $7,126 |
- | - | - | - | $3,430 | 1,234 |
- - kWh |
- - kW-months/year |
$3,430 1,234 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $301 Cost: $150 |
$135 | 5,800 | $166 | 25 | - | - |
$135 5,800 kWh |
$166 25 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4237 SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING |
Savings: $4,941 Cost: $765 |
$819 | 35,100 | $4,122 | 624 | - | - |
$819 35,100 kWh |
$4,122 624 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $32,157 Cost: $22,551 |
$17,516 | 748,200 | $11,211 | 1,697 | $3,430 | 1,234 | $17,516 748,200 kWh |
$11,211 1,697 kW-months/year |
$3,430 1,234 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $18,557 Cost: $9,860 |
$13,305 | 567,800 | $5,252 | 795 | - | - | $13,305 567,800 kWh |
$5,252 795 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |