Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Utah |
---|---|
Assessment Year | 2004 |
Principal Product | dialysis solutions |
NAICS | 339999 - All Other Miscellaneous Manufacturing |
SIC | 3999 - Manufacturing Industries, Nec |
Sales | $100,000,000-$500,000,000 |
# of Employees | 750 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 35,000,000 Pieces |
Production Hrs. Annual | 0 |
Location (State) | UT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,655,336 | 77,792,000 | kWh | $0.02 |
Electricity Demand | $770,839 | 121,392 | kW-months/year | $6.35 |
TOTAL ENERGY COSTS | $2,438,954 | |||
RECOMMENDED SAVINGS* | $1,625,803 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $238,600 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3417 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT |
Savings: $1,370,474 Cost: $22,000,000 |
$1,724,447 | 74,256,000 | $849,489 | 106,080 | $(-1,203,462) | (-278,386) | - | - | - | - | - | - |
$1,724,447 74,256,000 kWh |
$849,489 106,080 kW-months/year |
$(-1,203,462) (-278,386) MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $95,199 Cost: - |
$64,712 | 2,786,588 | $30,487 | 3,807 | - | - | - | - | - | - | - | - |
$64,712 2,786,588 kWh |
$30,487 3,807 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $16,729 Cost: $26,520 |
- | - | $16,729 | 2,089 | - | - | - | - | - | - | - | - |
- - kWh |
$16,729 2,089 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4112 RECOVERY METALS FROM RINSE WATER(EVAP., ION EXCHANGE, RO, ELECTROLYSIS, ELECTRODIALYSIS) AND REUSE RINSE WATER |
Savings: $73,401 Cost: $750,000 |
- | - | - | - | - | - | $12,919 | 58,705,900 | $60,482 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$12,919 58,705,900 Tgal |
$60,482 - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $70,000 Cost: $18,000 |
- | - | - | - | - | - | - | - | - | - | $70,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
$70,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $1,625,803 Cost: $22,794,520 |
$1,789,159 | 77,042,588 | $896,705 | 111,976 | $(-1,203,462) | (-278,386) | $12,919 | 58,705,900 | $60,482 | - | $70,000 | - | $1,789,159 77,042,588 kWh |
$896,705 111,976 kW-months/year |
$(-1,203,462) (-278,386) MMBtu |
$12,919 58,705,900 Tgal |
$60,482 - Tgal |
$70,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $238,600 Cost: $768,000 |
$64,712 | 2,786,588 | $30,487 | 3,807 | - | - | $12,919 | 58,705,900 | $60,482 | - | $70,000 | - | $64,712 2,786,588 kWh |
$30,487 3,807 kW-months/year |
- - MMBtu |
$12,919 58,705,900 Tgal |
$60,482 - Tgal |
$70,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption | One-time Revenue or Avoided Cost |