Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Utah |
---|---|
Assessment Year | 2005 |
Principal Product | tempura beef, chicken & pork |
NAICS | 311612 - Meat Processed from Carcasses |
SIC | 2013 - Sausages And Other Prepared Meats |
Sales | $10,000,000-$50,000,000 |
# of Employees | 85 |
Plant Area (Sq.Ft.) | 27,000 |
Annual Production | 5,000,000 Pounds |
Production Hrs. Annual | 2,600 |
Location (State) | ID |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $26,824 | 996,065 | kWh | $0.03 |
Electricity Demand | $7,815 | 2,771 | kW-months/year | $2.82 |
Natural Gas | $86,885 | 10,496 | MMBtu | $8.28 |
TOTAL ENERGY COSTS | $121,524 | |||
RECOMMENDED SAVINGS* | $358,812 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Primary Raw Material | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Primary Raw Material | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.113 INSTALL REFRIGERATION SYSTEM TO COOL PRODUCT |
Savings: $336,460 Cost: $336,000 |
- | - | - | - | - | - | $336,460 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$336,460 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7491 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS |
Savings: $727 Cost: $495 |
$617 | 18,568 | $110 | 34 | - | - | - | - | - | - |
$617 18,568 kWh |
$110 34 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2696 USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS |
Savings: $350 Cost: $2,000 |
$245 | 7,327 | $105 | 32 | - | - | - | - | - | - |
$245 7,327 kWh |
$105 32 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $19,080 Cost: - |
- | - | - | - | - | - | - | - | $19,080 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$19,080 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.8123 PAY UTILITY BILLS ON TIME |
Savings: $1,418 Cost: - |
- | - | - | - | - | - | - | - | $1,418 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$1,418 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $777 Cost: $2,000 |
- | - | - | - | $777 | 90 | - | - | - | - |
- - kWh |
- - kW-months/year |
$777 90 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $358,812 Cost: $340,495 |
$862 | 25,895 | $215 | 66 | $777 | 90 | $336,460 | - | $20,498 | - | $862 25,895 kWh |
$215 66 kW-months/year |
$777 90 MMBtu |
$336,460 - $ |
$20,498 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Primary Raw Material | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Primary Raw Material | One-time Revenue or Avoided Cost |