Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Utah |
---|---|
Assessment Year | 2021 |
Principal Product | Flexible packaging and labels |
NAICS | 326112 - Plastics Packaging Film and Sheet (including Laminated) Manufacturing |
SIC | 2671 - Paper Coated & Laminated, Packaging |
Sales | $10,000,000-$50,000,000 |
# of Employees | 70 |
Plant Area (Sq.Ft.) | 40,000 |
Annual Production | 1,000,000 Units |
Production Hrs. Annual | 6,032 |
Location (State) | UT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $64,339 | 1,306,550 | kWh | $0.05 |
Electricity Demand | $63,581 | 3,680 | kW-months/year | $17.28 |
Electricity Fees | $20,051 | - | $ | - |
Natural Gas | $29,821 | 4,774 | MMBtu | $6.25 |
TOTAL ENERGY COSTS | $198,966 | |||
RECOMMENDED SAVINGS* | $34,784 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $19,782 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $6,439 Cost: $15,243 |
$6,439 | 131,400 | - | - | - | - | - | - | - | - |
$6,439 131,400 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $5,200 Cost: $5,000 |
- | - | - | - | - | - | - | - | $5,200 | 152,941 |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$5,200 152,941 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $4,999 Cost: $3,792 |
- | - | - | - | $4,999 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,999 - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $4,803 Cost: $4,803 |
$4,803 | 98,020 | - | - | - | - | - | - | - | - |
$4,803 98,020 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,814 Cost: $7,952 |
$2,572 | 52,492 | $1,242 | 72 | - | - | - | - | - | - |
$2,572 52,492 kWh |
$1,242 72 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2622 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL |
Savings: $3,039 Cost: $17,334 |
$1,278 | 26,081 | $1,761 | 102 | - | - | - | - | - | - |
$1,278 26,081 kWh |
$1,761 102 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,543 Cost: $100 |
$1,715 | 34,995 | $828 | 48 | - | - | - | - | - | - |
$1,715 34,995 kWh |
$828 48 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,268 Cost: $212 |
$1,853 | 37,815 | $415 | 24 | - | - | - | - | - | - |
$1,853 37,815 kWh |
$415 24 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $1,679 Cost: $1,200 |
- | - | - | - | - | - | $1,679 | 269 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$1,679 269 MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $34,784 Cost: $55,636 |
$18,660 | 380,803 | $4,247 | 246 | $4,999 | - | $1,679 | 269 | $5,200 | 152,941 | $18,660 380,803 kWh |
$4,247 246 kW-months/year |
$4,999 - $ |
$1,679 269 MMBtu |
$5,200 152,941 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $19,782 Cost: $42,041 |
$13,857 | 282,783 | $4,247 | 246 | - | - | $1,679 | 269 | - | - | $13,857 282,783 kWh |
$4,247 246 kW-months/year |
- - $ |
$1,679 269 MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) |