Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Washington |
---|---|
Assessment Year | 2008 |
Principal Product | Tofu and Tofu Products |
NAICS | 311999 - All Other Miscellaneous Food Manufacturing |
SIC | 2099 - Food Preparations, Nec |
Sales | $1,000,000-$5,000,000 |
# of Employees | 22 |
Plant Area (Sq.Ft.) | 10,000 |
Annual Production | 540,000 Pounds |
Production Hrs. Annual | 3,510 |
Location (State) | HI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $14,635 | 73,415 | kWh | $0.20 |
Electricity Demand | $1,718 | 300 | kW-months/year | $5.73 |
Natural Gas | $82,543 | 2,419 | MMBtu | $34.12 |
TOTAL ENERGY COSTS | $161,084 | |||
RECOMMENDED SAVINGS* | $63,155 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $41,263 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $29,638 Cost: - |
- | - | - | - | $29,638 | - | - | - |
- - kWh |
- - kW-months/year |
$29,638 - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1224 REPLACE BOILER |
Savings: $10,000 Cost: $20,000 |
- | - | - | - | $10,000 | 1,001 | - | - |
- - kWh |
- - kW-months/year |
$10,000 1,001 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2113 REPAIR OR REPLACE STEAM TRAPS |
Savings: $5,490 Cost: $5,600 |
- | - | - | - | $5,490 | 700 | - | - |
- - kWh |
- - kW-months/year |
$5,490 700 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $7,000 Cost: $500 |
- | - | - | - | $7,000 | 548 | - | - |
- - kWh |
- - kW-months/year |
$7,000 548 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2523 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS |
Savings: $4,625 Cost: $8,550 |
$4,608 | 24,255 | $17 | 3 | - | - | - | - |
$4,608 24,255 kWh |
$17 3 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4156 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE |
Savings: $5,510 Cost: $10 |
- | - | - | - | - | - | $5,510 | 631,000 |
- - kWh |
- - kW-months/year |
- - MMBtu |
$5,510 631,000 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $892 Cost: - |
$808 | 4,255 | $84 | 15 | - | - | - | - |
$808 4,255 kWh |
$84 15 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $63,155 Cost: $34,660 |
$5,416 | 28,510 | $101 | 18 | $52,128 | 2,249 | $5,510 | 631,000 | $5,416 28,510 kWh |
$101 18 kW-months/year |
$52,128 2,249 MMBtu |
$5,510 631,000 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $41,263 Cost: $9,050 |
$4,608 | 24,255 | $17 | 3 | $36,638 | 548 | - | - | $4,608 24,255 kWh |
$17 3 kW-months/year |
$36,638 548 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal |