IAC Center | University of Washington |
---|---|
Assessment Year | 2009 |
Principal Product | Fiberglass Showers and Tubs |
NAICS | 327110 - Pottery, Ceramics, and Plumbing Fixture Manufacturing |
SIC | 3261 - Vitreous Plumbing Fixtures |
Sales | $50,000,000-$100,000,000 |
# of Employees | 152 |
Plant Area (Sq.Ft.) | 176,000 |
Annual Production | 50,000 Pieces |
Production Hrs. Annual | 3,000 |
Location (State) | WA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $325,375 | 4,042,864 | kWh | $0.08 |
Natural Gas | $401,079 | 40,238 | MMBtu | $9.97 |
TOTAL ENERGY COSTS | $726,454 | |||
RECOMMENDED SAVINGS* | $85,047 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $16,186 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2443 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR |
Savings: $52,500 Cost: $78,750 |
- | - | - | - | $52,500 | 5,250 | - | - |
- - kWh |
- - kW-months/year |
$52,500 5,250 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $16,361 Cost: $17,335 |
$11,161 | 186,025 | - | - | - | - | $5,200 | - |
$11,161 186,025 kWh |
- - kW-months/year |
- - MMBtu |
$5,200 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2211 USE OPTIMUM TEMPERATURE |
Savings: $13,200 Cost: $19,800 |
- | - | - | - | $13,200 | 1,320 | - | - |
- - kWh |
- - kW-months/year |
$13,200 1,320 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $2,986 Cost: $6,091 |
$1,199 | 19,985 | $1,787 | 81 | - | - | - | - |
$1,199 19,985 kWh |
$1,787 81 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $85,047 Cost: $121,976 |
$12,360 | 206,010 | $1,787 | 81 | $65,700 | 6,570 | $5,200 | - | $12,360 206,010 kWh |
$1,787 81 kW-months/year |
$65,700 6,570 MMBtu |
$5,200 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $16,186 Cost: $25,891 |
$1,199 | 19,985 | $1,787 | 81 | $13,200 | 1,320 | - | - | $1,199 19,985 kWh |
$1,787 81 kW-months/year |
$13,200 1,320 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes |