IAC Assessment: WM0014
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WM0014
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Wisconsin, Milwaukee
Assessment Year 2012
Principal Product Scientific glassware
NAICS 327215 - Glass Product Manufacturing Made of Purchased Glass
SIC 3231 - Products Of Purchased Glass
Sales $5,000,000-$10,000,000
# of Employees 30
Plant Area (Sq.Ft.) 44,000
Annual Production 5,181 Pieces
Production Hrs. Annual 6,000
Location (State) WI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $65,578 988,800 kWh $0.07
Electricity Demand $45,552 4,012 kW-months/year $11.35
Electricity Fees $14,709 - $ -
Natural Gas $13,416 1,584 MMBtu $8.47
TOTAL ENERGY COSTS $168,135
RECOMMENDED SAVINGS* $19,216 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $17,577
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Ancillary Material Cost Water Consumption Electricity Usage Electricity Demand Ancillary Material Cost Water Consumption
$ kWh $ kW-months/year $ $ $ Tgal
01: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION Savings:
$15,433
Cost:
$47,000
$(-12,889) (-194,400) $(-4,905) (-432) $8,783 - $24,444 - $(-12,889)
(-194,400)
kWh
$(-4,905)
(-432)
kW-months/year
$8,783
-
$
$24,444
-
Tgal
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$233
Cost:
$630
$233 3,515 - - - - - - $233
3,515
kWh
-
-
kW-months/year
-
-
$
-
-
Tgal
03: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,639
Cost:
$513
$1,639 24,730 - - - - - - $1,639
24,730
kWh
-
-
kW-months/year
-
-
$
-
-
Tgal
04: 4.463 MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS Savings:
$1,911
Cost:
$8,170
- - - - $1,911 - - - -
-
kWh
-
-
kW-months/year
$1,911
-
$
-
-
Tgal
TOTAL RECOMMENDED Savings:
$19,216
Cost:
$56,313
$(-11,017) (-166,155) $(-4,905) (-432) $10,694 - $24,444 - $(-11,017)
(-166,155)
kWh
$(-4,905)
(-432)
kW-months/year
$10,694
-
$
$24,444
-
Tgal
TOTAL IMPLEMENTED Savings:
$17,577
Cost:
$55,800
$(-12,656) (-190,885) $(-4,905) (-432) $10,694 - $24,444 - $(-12,656)
(-190,885)
kWh
$(-4,905)
(-432)
kW-months/year
$10,694
-
$
$24,444
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ $ $ Tgal
Electricity Usage Electricity Demand Ancillary Material Cost Water Consumption Electricity Usage Electricity Demand Ancillary Material Cost Water Consumption