Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2017 |
Principal Product | Treated wastewater |
NAICS | 221320 - Sewage Treatment Facilities |
SIC | 4952 - Sewerage Systems |
Sales | $1,000,000-$5,000,000 |
# of Employees | 5 |
Plant Area (Sq.Ft.) | 165,000 |
Annual Production | 1,642,500 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $193,175 | 3,967,397 | kWh | $0.05 |
Electricity Demand | $75,425 | 6,236 | kW-months/year | $12.10 |
Electricity Fees | $0 | - | $ | - |
Natural Gas | $57,087 | 11,149 | MMBtu | $5.12 |
TOTAL ENERGY COSTS | $325,687 | |||
RECOMMENDED SAVINGS* | $51,864 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $29,215 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.7311 MAINTAIN MACHINES TO REDUCE LEAKS |
Savings: $16,398 Cost: $20,000 |
$12,237 | 251,324 | $4,161 | 344 | - | - |
$12,237 251,324 kWh |
$4,161 344 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.9111 USE SOLAR HEAT TO HEAT MAKE-UP AIR |
Savings: $13,132 Cost: $72,000 |
$13,132 | 269,711 | - | - | - | - |
$13,132 269,711 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $5,735 Cost: $23,350 |
$4,284 | 87,989 | $1,451 | 120 | - | - |
$4,284 87,989 kWh |
$1,451 120 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $5,449 Cost: $332 |
$4,066 | 83,500 | $1,384 | 114 | - | - |
$4,066 83,500 kWh |
$1,384 114 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $4,330 Cost: $1,815 |
- | - | - | - | $4,330 | 846 |
- - kWh |
- - kW-months/year |
$4,330 846 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $3,167 Cost: $1,660 |
$2,363 | 48,532 | $804 | 67 | - | - |
$2,363 48,532 kWh |
$804 67 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,956 Cost: - |
$827 | 16,988 | $1,129 | 93 | - | - |
$827 16,988 kWh |
$1,129 93 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $1,082 Cost: $3,200 |
$756 | 15,516 | $327 | 27 | - | - |
$756 15,516 kWh |
$327 27 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $615 Cost: $73 |
$459 | 9,424 | $156 | 13 | - | - |
$459 9,424 kWh |
$156 13 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $51,864 Cost: $122,430 |
$38,123 | 782,984 | $9,411 | 778 | $4,330 | 846 | $38,123 782,984 kWh |
$9,411 778 kW-months/year |
$4,330 846 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $29,215 Cost: $25,347 |
$17,885 | 367,328 | $7,000 | 579 | $4,330 | 846 | $17,885 367,328 kWh |
$7,000 579 kW-months/year |
$4,330 846 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |