Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 1998 |
Principal Product | Rubber, plastic, bulk goods |
NAICS | n/a |
SIC | 3069 - Fabricated Rubber Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 90 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 585 Tons |
Production Hrs. Annual | 1,920 |
Location (State) | MD |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $255,751 | 3,633,353 | kWh | $0.07 |
Electricity Demand | $120,836 | 13,942 | kW-months/year | $8.67 |
Natural Gas | $385,291 | 132,601 | MMBtu | $2.91 |
TOTAL ENERGY COSTS | $761,878 | |||
RECOMMENDED SAVINGS* | $205,260 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Water Disposal | Administrative Changes | Electricity Usage | Natural Gas | Water Disposal | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT |
Savings: $1,075 Cost: $2,580 |
$1,075 | 28,722 | - | - | - | - | - | - |
$1,075 28,722 kWh |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $16,667 Cost: $9,432 |
- | - | $16,667 | 2,994 | - | - | - | - |
- - kWh |
$16,667 2,994 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $4,282 Cost: $5,130 |
- | - | $4,282 | 393 | - | - | - | - |
- - kWh |
$4,282 393 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $322 Cost: $482 |
- | - | $322 | 110 | - | - | - | - |
- - kWh |
$322 110 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2492 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR |
Savings: $162 Cost: $550 |
- | - | $162 | 77 | - | - | - | - |
- - kWh |
$162 77 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $142 Cost: $220 |
$142 | 3,810 | - | - | - | - | - | - |
$142 3,810 kWh |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.4115 RECOVER AND REUSE COOLING WATER |
Savings: $670 Cost: $1,525 |
- | - | - | - | $670 | - | - | - |
- - kWh |
- - MMBtu |
$670 - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) |
Savings: $1,940 Cost: $550 |
- | - | - | - | $1,940 | - | - | - |
- - kWh |
- - MMBtu |
$1,940 - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.521 CLEAR AND RENT EXISTING SPACE |
Savings: $180,000 Cost: $4,000 |
- | - | - | - | - | - | $180,000 | - |
- - kWh |
- - MMBtu |
- - Tgal |
$180,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $205,260 Cost: $24,469 |
$1,217 | 32,532 | $21,433 | 3,574 | $2,610 | - | $180,000 | - | $1,217 32,532 kWh |
$21,433 3,574 MMBtu |
$2,610 - Tgal |
$180,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Water Disposal | Administrative Changes | Electricity Usage | Natural Gas | Water Disposal | Administrative Changes |