Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2000 |
Principal Product | Laminated Wood |
NAICS | n/a |
SIC | 2421 - Sawmills And Planing Mills, General |
Sales | $100,000,000-$500,000,000 |
# of Employees | 320 |
Plant Area (Sq.Ft.) | 360,000 |
Annual Production | 5,000 Thousand Feet |
Production Hrs. Annual | 8,568 |
Location (State) | WV |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,808,501 | 46,726,847 | kWh | $0.04 |
Electricity Demand | $693,115 | 97,762 | kW-months/year | $7.09 |
Electricity Fees | $39,105 | - | $ | - |
Natural Gas | $313,911 | 91,018 | MMBtu | $3.45 |
TOTAL ENERGY COSTS | $2,854,632 | |||
RECOMMENDED SAVINGS* | $349,857 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $87,417 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Natural Gas | Solid Waste (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $6,707 Cost: $280 |
- | - | $6,707 | 1,944 | - | - | - | - |
- - kWh |
$6,707 1,944 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7314 REDUCE VENTILATION AIR |
Savings: $694 Cost: $1,170 |
- | - | $694 | 201 | - | - | - | - |
- - kWh |
$694 201 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2426 USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR |
Savings: $33,886 Cost: $10,000 |
- | - | $33,886 | 10,075 | - | - | - | - |
- - kWh |
$33,886 10,075 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,156 Cost: $220 |
$2,156 | 90,270 | - | - | - | - | - | - |
$2,156 90,270 kWh |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $40,958 Cost: $200 |
- | - | $40,958 | - | - | - | - | - |
- - kWh |
$40,958 - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS |
Savings: $4,706 Cost: $870 |
- | - | - | - | $4,706 | - | - | - |
- - kWh |
- - MMBtu |
$4,706 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $3,710 Cost: $11,000 |
- | - | - | - | $3,710 | - | - | - |
- - kWh |
- - MMBtu |
$3,710 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.445 INSTALL EQUIPMENT TO MOVE PRODUCT |
Savings: $257,040 Cost: $105,000 |
- | - | - | - | - | - | $257,040 | - |
- - kWh |
- - MMBtu |
- - lb |
$257,040 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $349,857 Cost: $128,740 |
$2,156 | 90,270 | $82,245 | 12,220 | $8,416 | - | $257,040 | - | $2,156 90,270 kWh |
$82,245 12,220 MMBtu |
$8,416 - lb |
$257,040 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $87,417 Cost: $21,700 |
$2,156 | 90,270 | $81,551 | 12,019 | $3,710 | - | - | - | $2,156 90,270 kWh |
$81,551 12,019 MMBtu |
$3,710 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Natural Gas | Solid Waste (non-haz) | Personnel Changes |