Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2000 |
Principal Product | Corrugated Packaging Material |
NAICS | n/a |
SIC | 2653 - Corrugated And Solid Fiber Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 97 |
Plant Area (Sq.Ft.) | 224,000 |
Annual Production | 400,000 Thousand Feet |
Production Hrs. Annual | 6,864 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $91,391 | 3,174,678 | kWh | $0.03 |
Electricity Demand | $60,260 | 8,838 | kW-months/year | $6.82 |
Electricity Fees | $110,265 | - | $ | - |
Natural Gas | $178,594 | 29,812 | MMBtu | $5.99 |
TOTAL ENERGY COSTS | $440,510 | |||
RECOMMENDED SAVINGS* | $73,789 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $39,455 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Water Disposal | Administrative Changes | Primary Product | Electricity Usage | Natural Gas | Water Disposal | Administrative Changes | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $1,154 Cost: $560 |
$1,154 | 18,171 | - | - | - | - | - | - | - | - |
$1,154 18,171 kWh |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $10,865 Cost: $4,220 |
- | - | $10,865 | 2,884 | - | - | - | - | - | - |
- - kWh |
$10,865 2,884 MMBtu |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $3,752 Cost: $169 |
- | - | $3,752 | 626 | - | - | - | - | - | - |
- - kWh |
$3,752 626 MMBtu |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4157 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM |
Savings: $1,768 Cost: $800 |
$1,768 | 23,740 | - | - | - | - | - | - | - | - |
$1,768 23,740 kWh |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,552 Cost: $500 |
- | - | $1,552 | 259 | - | - | - | - | - | - |
- - kWh |
$1,552 259 MMBtu |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $782 Cost: $416 |
$782 | 12,309 | - | - | - | - | - | - | - | - |
$782 12,309 kWh |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $22,060 Cost: - |
- | - | - | - | - | - | $22,060 | - | - | - |
- - kWh |
- - MMBtu |
- - Tgal |
$22,060 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,141 Cost: $23 |
$2,141 | 33,705 | - | - | - | - | - | - | - | - |
$2,141 33,705 kWh |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.4154 ELIMINATE LEAKS IN WATER LINES AND VALVES |
Savings: $15,135 Cost: $20,000 |
- | - | - | - | $15,135 | - | - | - | - | - |
- - kWh |
- - MMBtu |
$15,135 - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.521 CLEAR AND RENT EXISTING SPACE |
Savings: $6,000 Cost: $100 |
- | - | - | - | - | - | $6,000 | - | - | - |
- - kWh |
- - MMBtu |
- - Tgal |
$6,000 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 4.126 INSTALL SENSORS TO DETECT DEFECTS |
Savings: $8,580 Cost: $125 |
- | - | - | - | - | - | - | - | $8,580 | - |
- - kWh |
- - MMBtu |
- - Tgal |
- - $ |
$8,580 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $73,789 Cost: $26,913 |
$5,845 | 87,925 | $16,169 | 3,769 | $15,135 | - | $28,060 | - | $8,580 | - | $5,845 87,925 kWh |
$16,169 3,769 MMBtu |
$15,135 - Tgal |
$28,060 - $ |
$8,580 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $39,455 Cost: $1,677 |
$5,063 | 75,616 | $3,752 | 626 | - | - | $22,060 | - | $8,580 | - | $5,063 75,616 kWh |
$3,752 626 MMBtu |
- - Tgal |
$22,060 - $ |
$8,580 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Water Disposal | Administrative Changes | Primary Product | Electricity Usage | Natural Gas | Water Disposal | Administrative Changes | Primary Product |