Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2000 |
Principal Product | Potato Chips |
NAICS | n/a |
SIC | 2096 - Potato Chips And Similar Snacks |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 180,950 |
Annual Production | 16,500,000 Pounds |
Production Hrs. Annual | 6,732 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $99,750 | 3,850,528 | kWh | $0.03 |
Electricity Demand | $121,659 | 8,932 | kW-months/year | $13.62 |
Natural Gas | $349,672 | 75,067 | MMBtu | $4.66 |
TOTAL ENERGY COSTS | $571,081 | |||
RECOMMENDED SAVINGS* | $272,873 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $45,380 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Natural Gas | Solid Waste (non-haz) | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,112 Cost: $25 |
$3,112 | 120,164 | - | - | - | - | - | - |
$3,112 120,164 kWh |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $35,579 Cost: $8,440 |
- | - | $35,579 | 7,635 | - | - | - | - |
- - kWh |
$35,579 7,635 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $1,587 Cost: $727 |
$1,587 | 61,254 | - | - | - | - | - | - |
$1,587 61,254 kWh |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $471 Cost: $500 |
$471 | 18,171 | - | - | - | - | - | - |
$471 18,171 kWh |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4157 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM |
Savings: $2,070 Cost: $1,012 |
$2,070 | 41,032 | - | - | - | - | - | - |
$2,070 41,032 kWh |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $3,609 Cost: $636 |
- | - | $3,609 | 775 | - | - | - | - |
- - kWh |
$3,609 775 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $615 Cost: $500 |
$615 | 23,740 | - | - | - | - | - | - |
$615 23,740 kWh |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2426 USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR |
Savings: $32,382 Cost: $4,822 |
- | - | $32,382 | 6,949 | - | - | - | - |
- - kWh |
$32,382 6,949 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $34,531 Cost: - |
- | - | $34,531 | - | - | - | - | - |
- - kWh |
$34,531 - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.6126 DIRECT WASTE GASSES TO BOILER COMBUSTION AIR |
Savings: $56,401 Cost: $150,000 |
- | - | - | - | $56,401 | - | - | - |
- - kWh |
- - MMBtu |
$56,401 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $87,516 Cost: $120,000 |
- | - | - | - | - | - | $87,516 | - |
- - kWh |
- - MMBtu |
- - lb |
$87,516 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 4.424 IMPROVE SPACE COMFORT CONDITIONING |
Savings: $15,000 Cost: $901 |
- | - | - | - | - | - | $15,000 | - |
- - kWh |
- - MMBtu |
- - lb |
$15,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $272,873 Cost: $287,563 |
$7,855 | 264,361 | $106,101 | 15,359 | $56,401 | - | $102,516 | - | $7,855 264,361 kWh |
$106,101 15,359 MMBtu |
$56,401 - lb |
$102,516 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $45,380 Cost: $2,900 |
$7,240 | 240,621 | $38,140 | 775 | - | - | - | - | $7,240 240,621 kWh |
$38,140 775 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Natural Gas | Solid Waste (non-haz) | Administrative Changes |