Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2000 |
Principal Product | Hardwood lumber and furniture |
NAICS | n/a |
SIC | 2426 - Hardwood Dimension & Flooring Mills |
Sales | $10,000,000-$50,000,000 |
# of Employees | 210 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 20,000,000 Thousand Feet |
Production Hrs. Annual | 5,125 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $696,459 | 11,403,869 | kWh | $0.06 |
Electricity Demand | $178,301 | 29,804 | kW-months/year | $5.98 |
Electricity Fees | $160,257 | - | $ | - |
Natural Gas | $87,758 | 17,028 | MMBtu | $5.15 |
TOTAL ENERGY COSTS | $1,122,775 | |||
RECOMMENDED SAVINGS* | $138,597 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $26,003 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $132 Cost: $180 |
- | - | - | - | $132 | 149 | - | - | - | - |
- - kWh |
- - kW-months/year |
$132 149 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $5,907 Cost: $3,980 |
- | - | - | - | $5,907 | 1,147 | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,907 1,147 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $3,889 Cost: $1,000 |
- | - | - | - | $3,889 | 755 | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,889 755 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4157 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM |
Savings: $4,675 Cost: $800 |
$2,179 | 56,565 | $2,496 | 265 | - | - | - | - | - | - |
$2,179 56,565 kWh |
$2,496 265 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $1,544 Cost: $240 |
$1,322 | 34,291 | $222 | 24 | - | - | - | - | - | - |
$1,322 34,291 kWh |
$222 24 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,113 Cost: $720 |
$2,113 | 54,807 | - | - | - | - | - | - | - | - |
$2,113 54,807 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,718 Cost: $60 |
$3,718 | 96,424 | - | - | - | - | - | - | - | - |
$3,718 96,424 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $11,068 Cost: $300 |
- | - | - | - | $11,068 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$11,068 - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $922 Cost: $278 |
- | - | - | - | $922 | 179 | - | - | - | - |
- - kWh |
- - kW-months/year |
$922 179 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.2628 UTILIZE A LESS EXPENSIVE COOLING METHOD |
Savings: $1,435 Cost: $530 |
$1,435 | 37,222 | - | - | - | - | - | - | - | - |
$1,435 37,222 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.2625 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE |
Savings: $1,887 Cost: $40 |
$1,887 | 48,945 | - | - | - | - | - | - | - | - |
$1,887 48,945 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,057 Cost: $500 |
$2,057 | 53,341 | - | - | - | - | - | - | - | - |
$2,057 53,341 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $3,000 Cost: $600 |
- | - | - | - | - | - | $3,000 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$3,000 - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $56,250 Cost: $300 |
- | - | - | - | - | - | $56,250 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$56,250 - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
15: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $20,000 Cost: $300 |
- | - | - | - | - | - | $20,000 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$20,000 - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
16: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $20,000 Cost: $3,000 |
- | - | - | - | - | - | - | - | $20,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$20,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $138,597 Cost: $12,828 |
$14,711 | 381,595 | $2,718 | 289 | $21,918 | 2,230 | $79,250 | - | $20,000 | - | $14,711 381,595 kWh |
$2,718 289 kW-months/year |
$21,918 2,230 MMBtu |
$79,250 - lb |
$20,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $26,003 Cost: $2,398 |
$11,163 | 289,566 | $2,718 | 289 | $12,122 | 328 | - | - | - | - | $11,163 289,566 kWh |
$2,718 289 kW-months/year |
$12,122 328 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Primary Product |