Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2001 |
Principal Product | Rough Lumber |
NAICS | n/a |
SIC | 3531 - Construction Machinery |
Sales | $5,000,000-$10,000,000 |
# of Employees | 90 |
Plant Area (Sq.Ft.) | 23,150 |
Annual Production | 20,000 Thousand Feet |
Production Hrs. Annual | 4,590 |
Location (State) | WV |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $110,605 | 3,962,400 | kWh | $0.03 |
Electricity Demand | $84,793 | 794 | kW-months/year | $106.79 |
Wood | $28,688 | 67,664 | MMBtu | $0.42 |
TOTAL ENERGY COSTS | $224,086 | |||
RECOMMENDED SAVINGS* | $124,051 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $32,592 |
#|Description |
Savings Cost |
Status | Electricity Usage | Wood | Other Liquid (haz) | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Wood | Other Liquid (haz) | Solid Waste (non-haz) | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | gal | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,402 Cost: $40 |
$2,402 | 50,103 | - | - | - | - | - | - | - | - |
$2,402 50,103 kWh |
- - MMBtu |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2113 REPAIR OR REPLACE STEAM TRAPS |
Savings: $1,680 Cost: $2,680 |
- | - | $1,680 | 1,042 | - | - | - | - | - | - |
- - kWh |
$1,680 1,042 MMBtu |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $555 Cost: $588 |
- | - | $555 | 1,309 | - | - | - | - | - | - |
- - kWh |
$555 1,309 MMBtu |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3414 BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT |
Savings: $52,028 Cost: $185,000 |
$52,028 | 2,147,104 | - | - | - | - | - | - | - | - |
$52,028 2,147,104 kWh |
- - MMBtu |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $659 Cost: $150 |
$659 | 17,287 | - | - | - | - | - | - | - | - |
$659 17,287 kWh |
- - MMBtu |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4157 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM |
Savings: $7,955 Cost: $1,500 |
$7,955 | 170,819 | - | - | - | - | - | - | - | - |
$7,955 170,819 kWh |
- - MMBtu |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE |
Savings: $35,000 Cost: $1,500 |
- | - | - | - | - | - | $35,000 | - | - | - |
- - kWh |
- - MMBtu |
- - gal |
$35,000 - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.6124 BURN WASTE OIL FOR HEAT |
Savings: $3,772 Cost: $5,000 |
- | - | - | - | $3,772 | - | - | - | - | - |
- - kWh |
- - MMBtu |
$3,772 - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $20,000 Cost: $7,000 |
- | - | - | - | - | - | - | - | $20,000 | - |
- - kWh |
- - MMBtu |
- - gal |
- - lb |
$20,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $124,051 Cost: $203,458 |
$63,044 | 2,385,313 | $2,235 | 2,351 | $3,772 | - | $35,000 | - | $20,000 | - | $63,044 2,385,313 kWh |
$2,235 2,351 MMBtu |
$3,772 - gal |
$35,000 - lb |
$20,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $32,592 Cost: $11,808 |
$10,357 | 220,922 | $2,235 | 2,351 | - | - | - | - | $20,000 | - | $10,357 220,922 kWh |
$2,235 2,351 MMBtu |
- - gal |
- - lb |
$20,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | gal | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Wood | Other Liquid (haz) | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Wood | Other Liquid (haz) | Solid Waste (non-haz) | Administrative Changes |