Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2016 |
Principal Product | Products of Purchased Glass |
NAICS | 327215 - Glass Product Manufacturing Made of Purchased Glass |
SIC | 3231 - Products Of Purchased Glass |
Sales | $10,000,000-$50,000,000 |
# of Employees | 91 |
Plant Area (Sq.Ft.) | 114,000 |
Annual Production | 3,500,000 Pieces |
Production Hrs. Annual | 4,590 |
Location (State) | WV |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $127,301 | 1,775,520 | kWh | $0.07 |
Electricity Demand | $73,793 | 9,560 | kW-months/year | $7.72 |
Natural Gas | $10,607 | 1,183 | MMBtu | $8.97 |
TOTAL ENERGY COSTS | $211,701 | |||
RECOMMENDED SAVINGS* | $12,423 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,495 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $3,759 Cost: $1,510 |
$1,569 | 21,883 | $440 | 57 | - | - | $1,750 | - |
$1,569 21,883 kWh |
$440 57 kW-months/year |
- - MMBtu |
$1,750 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $3,281 Cost: $6,551 |
$2,563 | 35,746 | $718 | 93 | - | - | - | - |
$2,563 35,746 kWh |
$718 93 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $1,381 Cost: $3,265 |
- | - | - | - | $1,381 | 154 | - | - |
- - kWh |
- - kW-months/year |
$1,381 154 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,154 Cost: $77 |
$899 | 12,544 | $255 | 33 | - | - | - | - |
$899 12,544 kWh |
$255 33 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4157 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM |
Savings: $996 Cost: $1,000 |
$1,570 | 21,892 | $571 | 74 | - | - | $(-1,145) | - |
$1,570 21,892 kWh |
$571 74 kW-months/year |
- - MMBtu |
$(-1,145) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $888 Cost: $504 |
- | - | - | - | $888 | 99 | - | - |
- - kWh |
- - kW-months/year |
$888 99 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $560 Cost: $467 |
$398 | 5,548 | $162 | 21 | - | - | - | - |
$398 5,548 kWh |
$162 21 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $300 Cost: $543 |
$353 | 4,926 | $100 | 13 | - | - | $(-153) | - |
$353 4,926 kWh |
$100 13 kW-months/year |
- - MMBtu |
$(-153) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $104 Cost: $106 |
$81 | 1,130 | $23 | 3 | - | - | - | - |
$81 1,130 kWh |
$23 3 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $12,423 Cost: $14,023 |
$7,433 | 103,669 | $2,269 | 294 | $2,269 | 253 | $452 | - | $7,433 103,669 kWh |
$2,269 294 kW-months/year |
$2,269 253 MMBtu |
$452 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,495 Cost: $5,458 |
$3,301 | 46,040 | $1,111 | 144 | $1,381 | 154 | $(-1,298) | - | $3,301 46,040 kWh |
$1,111 144 kW-months/year |
$1,381 154 MMBtu |
$(-1,298) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||