Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2023 |
Principal Product | Skin care, hair color and hair care |
NAICS | 325620 - Toilet Preparation Manufacturing |
SIC | 2844 - Toilet Preparations |
Sales | $50,000,000-$100,000,000 |
# of Employees | 490 |
Plant Area (Sq.Ft.) | 140,000 |
Annual Production | 20,000 Tons |
Production Hrs. Annual | 6,120 |
Location (State) | MD |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $448,325 | 5,858,072 | kWh | $0.08 |
Electricity Demand | $42,998 | 9,862 | kW-months/year | $4.36 |
Electricity Fees | $2,328 | - | $ | - |
Natural Gas | $88,960 | 20,514 | MMBtu | $4.34 |
TOTAL ENERGY COSTS | $668,342 | |||
RECOMMENDED SAVINGS* | $114,417 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $23,719 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Water Disposal | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $27,969 Cost: $55,520 |
$25,039 | 327,310 | $2,930 | 672 | - | - | - | - | - | - | - | - |
$25,039 327,310 kWh |
$2,930 672 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $23,931 Cost: $31,118 |
$5,235 | 68,426 | $628 | 144 | - | - | $9,803 | 1,586 | $8,265 | 1,586 | - | - |
$5,235 68,426 kWh |
$628 144 kW-months/year |
- - MMBtu |
$9,803 1,586 Tgal |
$8,265 1,586 Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1224 REPLACE BOILER |
Savings: $19,921 Cost: $90,000 |
- | - | - | - | $19,921 | 4,590 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$19,921 4,590 MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT |
Savings: $14,368 Cost: $70,000 |
$13,583 | 177,558 | $785 | 180 | - | - | - | - | - | - | - | - |
$13,583 177,558 kWh |
$785 180 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $5,435 Cost: $1,980 |
$4,890 | 63,917 | $545 | 125 | - | - | - | - | - | - | - | - |
$4,890 63,917 kWh |
$545 125 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4157 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM |
Savings: $5,167 Cost: $1,500 |
$5,713 | 74,678 | $637 | 146 | - | - | - | - | - | - | $(-1,183) | - |
$5,713 74,678 kWh |
$637 146 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
$(-1,183) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2425 USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER |
Savings: $4,509 Cost: $11,550 |
- | - | - | - | $4,509 | 1,039 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,509 1,039 MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $3,587 Cost: $3,721 |
$2,180 | 28,503 | $244 | 56 | $1,163 | 268 | - | - | - | - | - | - |
$2,180 28,503 kWh |
$244 56 kW-months/year |
$1,163 268 MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $2,563 Cost: $5,683 |
$2,845 | 37,187 | $318 | 73 | - | - | - | - | - | - | $(-600) | - |
$2,845 37,187 kWh |
$318 73 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
$(-600) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $2,313 Cost: $3,080 |
$1,982 | 25,909 | $331 | 76 | - | - | - | - | - | - | - | - |
$1,982 25,909 kWh |
$331 76 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $2,222 Cost: $1,250 |
- | - | - | - | $2,222 | 512 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,222 512 MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,386 Cost: $200 |
$1,246 | 16,287 | $140 | 32 | - | - | - | - | - | - | - | - |
$1,246 16,287 kWh |
$140 32 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $807 Cost: $970 |
- | - | - | - | $807 | 186 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$807 186 MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $239 Cost: $503 |
- | - | - | - | $239 | 55 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$239 55 MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $114,417 Cost: $277,075 |
$62,713 | 819,775 | $6,558 | 1,504 | $28,861 | 6,650 | $9,803 | 1,586 | $8,265 | 1,586 | $(-1,783) | - | $62,713 819,775 kWh |
$6,558 1,504 kW-months/year |
$28,861 6,650 MMBtu |
$9,803 1,586 Tgal |
$8,265 1,586 Tgal |
$(-1,783) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $23,719 Cost: $18,887 |
$18,856 | 246,481 | $2,215 | 508 | $4,431 | 1,021 | - | - | - | - | $(-1,783) | - | $18,856 246,481 kWh |
$2,215 508 kW-months/year |
$4,431 1,021 MMBtu |
- - Tgal |
- - Tgal |
$(-1,783) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Water Disposal | Personnel Changes |