IAC logo
IAC Implementation Rates
Sponsored by:
DOE MESC
IAC logo
IAC Implementation Rates
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The IAC implementation rates page provides a breakdown of rates based on the following criteria.
Reset
NAICS 3212 Veneer, Plywood, and Engineered Wood Product Manufacturing
Average Implementation Rate for All Matching Recommendations: 66.7%


Total Recommendations Total Implementation Status Known Implemented Imped Implementation Rate Imp Rate Implementation Status Unknown
1981 - - - - -
1982 - - - - -
1983 - - - - -
1984 - - - - -
1985 - - - - -
1986 - - - - -
1987 - - - - -
1988 - - - - -
1989 - - - - -
1990 - - - - -
1991 - - - - -
1992 - - - - -
1993 - - - - -
1994 - - - - -
1995 - - - - -
1996 - - - - -
1997 - - - - -
1998 - - - - -
1999 - - - - -
2000 - - - - -
2001 - - - - -
2002 - - - - -
2003 12 12 9 75.0% -
2004 11 11 7 63.6% -
2005 - - - - -
2006 - - - - -
2007 - - - - -
2008 - - - - -
2009 - - - - -
2010 13 13 8 61.5% -
2011 - - - - -
2012 - - - - -
2013 - - - - -
2014 - - - - -
2015 - - - - -
2016 - - - - -
2017 - - - - -
2018 - - - - -
2019 - - - - -
2020 - - - - -
2021 - - - - -
2022 - - - - -
2023 - - - - -
2024 - - - - -