IAC logo
IAC Implementation Rates
Sponsored by:
DOE MESC
IAC logo
IAC Implementation Rates
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The IAC implementation rates page provides a breakdown of rates based on the following criteria.
Reset
Average Implementation Rate for All Matching Recommendations: 39.4%


Total Recommendations Total Implementation Status Known Implemented Imped Implementation Rate Imp Rate Implementation Status Unknown
1981 - - - - -
1982 - - - - -
1983 - - - - -
1984 - - - - -
1985 - - - - -
1986 - - - - -
1987 - - - - -
1988 - - - - -
1989 - - - - -
1990 - - - - -
1991 - - - - -
1992 - - - - -
1993 - - - - -
1994 - - - - -
1995 - - - - -
1996 - - - - -
1997 - - - - -
1998 - - - - -
1999 - - - - -
2000 - - - - -
2001 - - - - -
2002 - - - - -
2003 35 35 15 42.9% -
2004 8 8 3 37.5% -
2005 33 33 20 60.6% -
2006 19 19 6 31.6% -
2007 42 42 13 31.0% -
2008 40 40 16 40.0% -
2009 31 31 13 41.9% -
2010 46 46 14 30.4% -
2011 - - - - -
2012 - - - - -
2013 - - - - -
2014 - - - - -
2015 - - - - -
2016 - - - - -
2017 - - - - -
2018 - - - - -
2019 - - - - -
2020 - - - - -
2021 - - - - -
2022 - - - - -
2023 - - - - -
2024 - - - - -
2025 - - - - -