IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

50

matching recommendations
Reset
NAICS 221 Utilities
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1097 # 04 Y:2023 04 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $19,348 $189,810 n/a
OK1097 # 03 Y:2023 03 2023 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $310 $291 n/a
OK1097 # 02 Y:2023 02 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,461 $2,074 n/a
OK1097 # 01 Y:2023 01 2023 USE EXISTING DAM TO GENERATE ELECTRICITY $9,070 $42,900 n/a
OK1090 # 05 Y:2023 05 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $68,844 $438,000 Not Implemented
OK1090 # 01 Y:2023 01 2023 USE COUNTER CURRENT RINSING TO REDUCE WASTE WATER $76,727 $51,456 Implemented
OK1090 # 02 Y:2023 02 2023 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $172 $530 Implemented
OK1090 # 04 Y:2023 04 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,316 $3,638 Implemented
OK1090 # 03 Y:2023 03 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,602 $1,797 Implemented
OK1075 # 01 Y:2022 01 2022 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,542 $3,232 Not Implemented
OK1075 # 04 Y:2022 04 2022 USE EXISTING DAM TO GENERATE ELECTRICITY $11,887 $59,000 Not Implemented
OK1075 # 02 Y:2022 02 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $168 $855 Implemented
OK1075 # 05 Y:2022 05 2022 USE SOLAR HEAT TO MAKE ELECTRICTY $40,136 $191,438 Not Implemented
OK1075 # 03 Y:2022 03 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,262 $7,150 Not Implemented
OK1058 # 03 Y:2021 03 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,252 $7,778 Implemented
OK1058 # 04 Y:2021 04 2021 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $185 $700 Implemented
OK1058 # 02 Y:2021 02 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $455 $2,130 Not Implemented
OK1058 # 01 Y:2021 01 2021 OPTIMIZE PLANT POWER FACTOR $1,800 $3,000 Not Implemented
OK1056 # 01 Y:2021 01 2021 RECOVER AND REUSE WASTE MATERIAL $10,400 $0 Not Implemented
OK1056 # 04 Y:2021 04 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $46 $162 Implemented
OK1056 # 03 Y:2021 03 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $425 $629 Implemented
OK1056 # 02 Y:2021 02 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,775 $3,987 Not Implemented
OK1038 # 02 Y:2021 02 2021 USE COUNTER CURRENT RINSING TO REDUCE WASTE WATER $24,443 $2,171 Not Implemented
OK1038 # 01 Y:2021 01 2021 INSTALL OCCUPANCY SENSORS $563 $1,944 Not Implemented
OK1038 # 03 Y:2021 03 2021 INSTALL TIMERS AND/OR THERMOSTATS $991 $0 Not Implemented