Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
102
matching recommendationsNAICS | 31135 | Chocolate and Confectionery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0625 # 11 Y:2024 | 11 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $177,385 | $2,104,448 | n/a |
SF0625 # 04 Y:2024 | 04 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,071 | $854 | n/a |
SF0625 # 07 Y:2024 | 07 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,943 | $10,277 | n/a |
SF0625 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,576 | $3,859 | n/a |
SF0625 # 02 Y:2024 | 02 | 2024 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $8,680 | $588 | n/a |
SF0625 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,669 | $0 | n/a |
SF0625 # 10 Y:2024 | 10 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,369 | $7,928 | n/a |
SF0625 # 03 Y:2024 | 03 | 2024 | REPAIR AND ELIMINATE STEAM LEAKS | $8,671 | $516 | n/a |
SF0625 # 09 Y:2024 | 09 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $14,307 | $15,295 | n/a |
SF0625 # 08 Y:2024 | 08 | 2024 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $155,547 | $160,389 | n/a |
SF0625 # 05 Y:2024 | 05 | 2024 | INCREASE AMOUNT OF CONDENSATE RETURNED | $26,010 | $8,735 | n/a |
SJ0005 # 05 Y:2023 | 05 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $854 | $658 | Not Implemented |
SJ0005 # 04 Y:2023 | 04 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,251 | $4,556 | Not Implemented |
SJ0005 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,218 | $962 | Implemented |
SJ0005 # 06 Y:2023 | 06 | 2023 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $5,992 | $2,536 | Implemented |
SJ0005 # 03 Y:2023 | 03 | 2023 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $270 | $0 | Not Implemented |
SJ0005 # 02 Y:2023 | 02 | 2023 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $23,445 | $5,613 | Not Implemented |
SF0572 # 08 Y:2021 | 08 | 2021 | USE SOLAR HEAT TO MAKE ELECTRICTY | $343,451 | $2,394,442 | Not Implemented |
SF0572 # 07 Y:2021 | 07 | 2021 | REPLACE BOILER | $14,321 | $72,000 | Not Implemented |
SF0572 # 06 Y:2021 | 06 | 2021 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,350 | $4,996 | Not Implemented |
SF0572 # 05 Y:2021 | 05 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $46,961 | $45,208 | Not Implemented |
SF0572 # 04 Y:2021 | 04 | 2021 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $33,236 | $25,695 | Not Implemented |
SF0572 # 02 Y:2021 | 02 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,781 | $1,200 | Implemented |
SF0572 # 01 Y:2021 | 01 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $16,373 | $200 | Implemented |
SF0572 # 10 Y:2021 | 10 | 2021 | INSTALL SUB-METERING EQUIPMENT | $8,446 | $6,896 | Implemented |