Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
12
matching recommendationsNAICS | 311520 | Ice Cream and Frozen Dessert Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0290 # 01 Y:2009 | 01 | 2009 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $9,385 | $1,200 | Not Implemented |
LE0290 # 02 Y:2009 | 02 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,837 | $15,700 | Not Implemented |
LE0290 # 03 Y:2009 | 03 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,929 | $2,000 | Not Implemented |
LE0290 # 04 Y:2009 | 04 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,543 | $750 | Implemented |
LE0290 # 05 Y:2009 | 05 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,148 | $152 | Not Implemented |
LE0290 # 06 Y:2009 | 06 | 2009 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $1,400 | $500 | Not Implemented |
LE0290 # 07 Y:2009 | 07 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,267 | $0 | Implemented |
LE0290 # 08 Y:2009 | 08 | 2009 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $1,204 | $2,500 | Implemented |
LE0290 # 09 Y:2009 | 09 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,150 | $2,500 | Implemented |
LE0290 # 10 Y:2009 | 10 | 2009 | INSTALL OCCUPANCY SENSORS | $1,045 | $0 | Implemented |
LE0290 # 11 Y:2009 | 11 | 2009 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $900 | $1,500 | Not Implemented |
LE0290 # 12 Y:2009 | 12 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $990 | $2,500 | Implemented |