IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

18

matching recommendations
Reset
NAICS 32221 Paperboard Container Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0810 # 05 Y:2011 05 2011 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $2,915 $0 Not Implemented
OK0810 # 04 Y:2011 04 2011 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $5,317 $0 Implemented
OK0810 # 03 Y:2011 03 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,360 $14,062 Not Implemented
OK0810 # 02 Y:2011 02 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $44,840 $11,400 Implemented
OK0810 # 01 Y:2011 01 2011 USE DIRECT FLAME IMPINGEMENT OR INFRARED PROCESSING FOR CHAMBER TYPE HEATING $41,808 $12,400 Not Implemented
OK0808 # 03 Y:2011 03 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $8,547 $17,879 Implemented
OK0808 # 06 Y:2011 06 2011 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $27,934 $5,125 Implemented
OK0808 # 05 Y:2011 05 2011 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $23,465 $16,400 Not Implemented
OK0808 # 04 Y:2011 04 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,907 $5,105 Implemented
OK0808 # 02 Y:2011 02 2011 USE POWER DURING OFF-PEAK PERIODS $19,801 $226 Implemented
OK0808 # 01 Y:2011 01 2011 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $11,989 $1,776 Not Implemented
MS0222 # 01 Y:2003 01 2003 PREHEAT COMBUSTION AIR WITH WASTE HEAT $11,730 $8,788 Not Implemented
MS0222 # 07 Y:2003 07 2003 USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT $1,680 $400 Not Implemented
MS0222 # 06 Y:2003 06 2003 TURN OFF EQUIPMENT WHEN NOT IN USE $1,717 $1,717 Not Implemented
MS0222 # 05 Y:2003 05 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,994 $0 Not Implemented
MS0222 # 04 Y:2003 04 2003 USE RADIANT HEATER FOR SPOT HEATING $2,158 $1,649 Not Implemented
MS0222 # 03 Y:2003 03 2003 REPAIR AND ELIMINATE STEAM LEAKS $2,178 $90 Implemented
MS0222 # 02 Y:2003 02 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,928 $196 Implemented