Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
923
matching recommendationsNAICS | 3259 | Other Chemical Product and Preparation Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0674 # 06 Y:2024 | 06 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $562 | $2,318 | n/a |
WV0674 # 03 Y:2024 | 03 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,331 | $12,440 | n/a |
WV0674 # 07 Y:2024 | 07 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $393 | $122 | n/a |
WV0674 # 04 Y:2024 | 04 | 2024 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $696 | $1,133 | n/a |
WV0674 # 05 Y:2024 | 05 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $658 | $3,214 | n/a |
WV0674 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,766 | $8,674 | n/a |
WV0674 # 09 Y:2024 | 09 | 2024 | INSULATE BARE EQUIPMENT | $148 | $482 | n/a |
WV0674 # 08 Y:2024 | 08 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $225 | $88 | n/a |
WV0674 # 02 Y:2024 | 02 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,374 | $8,262 | n/a |
SD0661 # 08 Y:2024 | 08 | 2024 | ADOPT IN-HOUSE MATERIAL GENERATION | $809,075 | $47,546 | n/a |
SD0661 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,348 | $676 | n/a |
SD0661 # 13 Y:2024 | 13 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,043 | $19,842 | n/a |
SD0661 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $641,754 | $589,764 | n/a |
SD0661 # 06 Y:2024 | 06 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,354 | $0 | n/a |
SD0661 # 05 Y:2024 | 05 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $10,205 | $0 | n/a |
SD0661 # 02 Y:2024 | 02 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $1,321,862 | $54,390 | n/a |
SD0661 # 11 Y:2024 | 11 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $970 | $1,863 | n/a |
SD0661 # 07 Y:2024 | 07 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $854 | $250 | n/a |
SD0661 # 04 Y:2024 | 04 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $3,584 | $4,191 | n/a |
SD0661 # 12 Y:2024 | 12 | 2024 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $12,725 | $11,775 | n/a |
SD0661 # 09 Y:2024 | 09 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,243 | $7,340 | n/a |
SD0661 # 10 Y:2024 | 10 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,652 | $2,148 | n/a |
WV0669 # 08 Y:2024 | 08 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,886 | $1,088 | n/a |
WV0669 # 09 Y:2024 | 09 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $3,954 | $10,900 | n/a |
WV0669 # 11 Y:2024 | 11 | 2024 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,467 | $940 | n/a |