Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
95
matching recommendationsNAICS | 32619 | Other Plastics Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0930 # 01 Y:2015 | 01 | 2015 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $137,102 | $90,000 | Not Implemented |
OK0930 # 02 Y:2015 | 02 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $17,351 | $10,800 | Not Implemented |
OK0883 # 08 Y:2014 | 08 | 2014 | USE RADIANT HEATER FOR SPOT HEATING | $7,584 | $15,000 | Not Implemented |
OK0883 # 03 Y:2014 | 03 | 2014 | INSTALL OCCUPANCY SENSORS | $2,502 | $2,480 | Not Implemented |
OK0883 # 04 Y:2014 | 04 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $445 | $2,048 | Not Implemented |
OK0883 # 01 Y:2014 | 01 | 2014 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $906 | $463 | Not Implemented |
OK0883 # 12 Y:2014 | 12 | 2014 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $23,778 | $19,100 | Not Implemented |
OK0883 # 11 Y:2014 | 11 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $221 | $1,083 | Not Implemented |
OK0883 # 09 Y:2014 | 09 | 2014 | OPTIMIZE PLANT POWER FACTOR | $8,198 | $18,876 | Not Implemented |
OK0883 # 10 Y:2014 | 10 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,481 | $30,000 | Not Implemented |
OK0883 # 07 Y:2014 | 07 | 2014 | INSTALL TIMERS AND/OR THERMOSTATS | $4,226 | $2,681 | Not Implemented |
OK0883 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $925 | $1,510 | Implemented |
OK0883 # 06 Y:2014 | 06 | 2014 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $3,030 | $980 | Implemented |
OK0883 # 02 Y:2014 | 02 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,972 | $1,750 | Not Implemented |
OK0882 # 11 Y:2014 | 11 | 2014 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $5,834 | $6,336 | Not Implemented |
OK0882 # 01 Y:2014 | 01 | 2014 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $4,763 | $1,400 | Implemented |
OK0882 # 04 Y:2014 | 04 | 2014 | INSTALL SET-BACK TIMERS | $142 | $170 | Not Implemented |
OK0882 # 06 Y:2014 | 06 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $634 | $2,940 | Not Implemented |
OK0882 # 05 Y:2014 | 05 | 2014 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $1,361 | $28 | Not Implemented |
OK0882 # 03 Y:2014 | 03 | 2014 | INSTALL TIMERS AND/OR THERMOSTATS | $8,378 | $2,870 | Not Implemented |
OK0882 # 02 Y:2014 | 02 | 2014 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $37,574 | $29,200 | Not Implemented |
OK0882 # 07 Y:2014 | 07 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,055 | $0 | Not Implemented |
OK0882 # 09 Y:2014 | 09 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,908 | $1,113 | Not Implemented |
OK0882 # 10 Y:2014 | 10 | 2014 | TURN OFF EQUIPMENT WHEN NOT IN USE | $333 | $0 | Implemented |
OK0882 # 08 Y:2014 | 08 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,060 | $1,025 | Implemented |