Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,191
matching recommendationsNAICS | 3363 | Motor Vehicle Parts Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0314 # 05 Y:2024 | 05 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,118 | $21,260 | n/a |
TT0314 # 04 Y:2024 | 04 | 2024 | SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING | $8,319 | $9,842 | n/a |
TT0314 # 02 Y:2024 | 02 | 2024 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $36,167 | $16,000 | n/a |
TT0314 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,281 | $1,500 | n/a |
TT0314 # 01 Y:2024 | 01 | 2024 | UPGRADE OBSOLETE EQUIPMENT | $51,299 | $312,500 | n/a |
TT0314 # 07 Y:2024 | 07 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,112 | $0 | n/a |
TT0314 # 06 Y:2024 | 06 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,036 | $8,059 | n/a |
TT0314 # 08 Y:2024 | 08 | 2024 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $1,111 | $4,500 | n/a |
IP0182 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,142 | $0 | n/a |
IP0182 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $950 | $1,284 | n/a |
IP0182 # 03 Y:2023 | 03 | 2023 | INSTALL OCCUPANCY SENSORS | $203 | $172 | n/a |
IP0182 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,891 | $50 | n/a |
IP0182 # 05 Y:2023 | 05 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,173 | $6,828 | n/a |
MU0040 # 01 Y:2023 | 01 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $106,121 | $1,404,000 | n/a |
MU0040 # 02 Y:2023 | 02 | 2023 | INSTALL OCCUPANCY SENSORS | $213 | $315 | n/a |
MU0040 # 04 Y:2023 | 04 | 2023 | MINIMIZE WATER USAGE | $68,486 | $150,124 | n/a |
MU0040 # 05 Y:2023 | 05 | 2023 | PAY BILLS ON TIME TO AVOID LATE FEES | $2,306 | $0 | n/a |
MU0040 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,004 | $41 | n/a |
MU0043 # 05 Y:2023 | 05 | 2023 | KEEP EQUIPMENT CLEAN | $33 | $0 | n/a |
MU0043 # 09 Y:2023 | 09 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $18,979 | $158,490 | n/a |
MU0043 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,700 | $7,887 | n/a |
MU0043 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $228 | $480 | n/a |
MU0043 # 07 Y:2023 | 07 | 2023 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $54 | $51 | n/a |
MU0043 # 01 Y:2023 | 01 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $116 | $319 | n/a |
MU0043 # 06 Y:2023 | 06 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $20,803 | $28,063 | n/a |