IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

67

matching recommendations
Reset
SIC 201 Meat Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LS2311 # 05 Y:2023 05 2023 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $11,014 $39,200 Implemented
LS2311 # 01 Y:2023 01 2023 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,616 $25 Implemented
LS2311 # 03 Y:2023 03 2023 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $3,096 $3,700 Implemented
LS2311 # 04 Y:2023 04 2023 REPLACE BOILER $81,818 $210,000 Not Implemented
LS2311 # 02 Y:2023 02 2023 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $3,795 $560 Implemented
LS1809 # 04 Y:2018 04 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,902 $4,019 Not Implemented
LS1809 # 01 Y:2018 01 2018 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,090 $100 Not Implemented
LS1809 # 03 Y:2018 03 2018 INSTALL OCCUPANCY SENSORS $401 $300 Not Implemented
LS1809 # 02 Y:2018 02 2018 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $134 $45 Not Implemented
LS1809 # 05 Y:2018 05 2018 INSULATE BARE EQUIPMENT $364 $440 Not Implemented
LS1809 # 06 Y:2018 06 2018 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $33 $50 Not Implemented
LS1809 # 07 Y:2018 07 2018 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $6,145 $11,000 Not Implemented
LS0002 # 01 Y:2017 01 2017 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $7,531 $0 Not Implemented
LS0002 # 06 Y:2017 06 2017 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $8,736 $0 Not Implemented
LS0002 # 04 Y:2017 04 2017 IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS $16,140 $0 Not Implemented
LS0002 # 05 Y:2017 05 2017 INSTALL FLOATING COVERS ON TANKS OF VOLATILE MATERIALS TO REDUCE EVAPORATION $271,330 $0 Not Implemented
LS0002 # 03 Y:2017 03 2017 INSTALL / REPAIR INSULATION ON STEAM LINES $1,124 $0 Not Implemented
LS0002 # 02 Y:2017 02 2017 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $33,634 $0 Not Implemented
LL0303 # 05 Y:2008 05 2008 INSTALL OCCUPANCY SENSORS $321 $60 Not Implemented
LL0303 # 04 Y:2008 04 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $764 $660 Implemented
LL0303 # 03 Y:2008 03 2008 INSULATE BARE EQUIPMENT $819 $999 Implemented
LL0303 # 01 Y:2008 01 2008 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,534 $30 Not Implemented
LL0303 # 02 Y:2008 02 2008 REPAIR AND ELIMINATE STEAM LEAKS $1,121 $730 Implemented
LL0303 # 06 Y:2008 06 2008 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $232 $33 Not Implemented
LL0257 # 03 Y:2006 03 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $20,217 $7,960 Not Implemented