IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

131

matching recommendations
Reset
SIC 201 Meat Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NL0086 # 02 Y:2023 02 2023 INSULATE BARE EQUIPMENT $6,202 $6,211 Implemented
NL0086 # 05 Y:2023 05 2023 KEEP EQUIPMENT CLEAN $350 $450 Not Implemented
NL0086 # 03 Y:2023 03 2023 METER WASTE WATER $4,239 $1,348 Implemented
NL0086 # 01 Y:2023 01 2023 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $48,136 $100,000 Not Implemented
NL0086 # 04 Y:2023 04 2023 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $573 $510 Not Implemented
NL0075 # 01 Y:2022 01 2022 AIR CONDITION ONLY SPACE NECESSARY $13,412 $7,500 Implemented
NL0075 # 05 Y:2022 05 2022 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $635 $575 Not Implemented
NL0075 # 03 Y:2022 03 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,087 $1,652 Implemented
NL0075 # 02 Y:2022 02 2022 RECOVER WASTE HEAT FROM EQUIPMENT $7,755 $28,900 Not Implemented
NL0075 # 04 Y:2022 04 2022 INSULATE BARE EQUIPMENT $980 $404 Implemented
NL0071 # 06 Y:2022 06 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,447 $4,500 Implemented
NL0071 # 03 Y:2022 03 2022 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $21,879 $30,410 Implemented
NL0071 # 04 Y:2022 04 2022 RECOVER WASTE HEAT FROM EQUIPMENT $3,139 $8,000 Not Implemented
NL0071 # 07 Y:2022 07 2022 INSULATE BARE EQUIPMENT $407 $2,521 Implemented
NL0071 # 05 Y:2022 05 2022 INSULATE BARE EQUIPMENT $2,400 $9,724 Implemented
NL0071 # 02 Y:2022 02 2022 MINIMIZE WATER USAGE $106,955 $72,150 Implemented
NL0071 # 01 Y:2022 01 2022 REPLACE BOILER $280,847 $220,000 Not Implemented
NL0047 # 05 Y:2020 05 2020 RECOVER AND REUSE WASTE MATERIAL $925 $5,160 Not Implemented
NL0047 # 01 Y:2020 01 2020 MINIMIZE WATER USAGE $75,018 $1,383 Not Implemented
NL0047 # 03 Y:2020 03 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $10,600 $6,024 Implemented
NL0047 # 07 Y:2020 07 2020 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $301 $1,148 Implemented
NL0047 # 06 Y:2020 06 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $643 $1,700 Implemented
NL0047 # 02 Y:2020 02 2020 METER WASTE WATER $41,210 $15,000 Implemented
NL0047 # 04 Y:2020 04 2020 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,234 $230 Implemented
NL0039 # 05 Y:2019 05 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,739 $1,600 Implemented