Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17
matching recommendationsSIC | 2023 | Dry, Condensed, Evaporated Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0067 # 02 Y:1995 | 02 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $375 | $795 | Implemented |
SF0067 # 03 Y:1995 | 03 | 1995 | INSTALL OCCUPANCY SENSORS | $3,408 | $1,478 | Implemented |
SF0067 # 04 Y:1995 | 04 | 1995 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,075 | $0 | Implemented |
SF0067 # 05 Y:1995 | 05 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $758 | $450 | Implemented |
SF0067 # 06 Y:1995 | 06 | 1995 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $33,872 | $6,773 | Not Implemented |
SF0067 # 07 Y:1995 | 07 | 1995 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $696 | $850 | Implemented |
SF0067 # 08 Y:1995 | 08 | 1995 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,803 | $0 | Implemented |
SF0067 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,292 | $6,960 | Implemented |
WI0232 # 09 Y:1995 | 09 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $139 | $0 | Not Implemented |
WI0232 # 08 Y:1995 | 08 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $244 | $640 | Not Implemented |
WI0232 # 07 Y:1995 | 07 | 1995 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $401 | $260 | Not Implemented |
WI0232 # 06 Y:1995 | 06 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $188 | $0 | Not Implemented |
WI0232 # 05 Y:1995 | 05 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,246 | $1,805 | Not Implemented |
WI0232 # 04 Y:1995 | 04 | 1995 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,004 | $0 | Not Implemented |
WI0232 # 03 Y:1995 | 03 | 1995 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,427 | $20 | Not Implemented |
WI0232 # 02 Y:1995 | 02 | 1995 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,343 | $10,000 | Not Implemented |
WI0232 # 01 Y:1995 | 01 | 1995 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,507 | $500 | Not Implemented |