IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

26

matching recommendations
Reset
SIC 2045 Prepared Flour Mixes And Doughs
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MZ0156 # 08 Y:2014 08 2014 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $11,299 $10,282 Implemented
MZ0156 # 07 Y:2014 07 2014 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $31,514 $141,366 Implemented
MZ0156 # 06 Y:2014 06 2014 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $1,337 $676 Not Implemented
MZ0156 # 05 Y:2014 05 2014 USE OPTIMUM THICKNESS INSULATION $9,068 $30,128 Implemented
MZ0156 # 04 Y:2014 04 2014 RECOVER WASTE HEAT FROM EQUIPMENT $2,886 $4,400 Implemented
MZ0156 # 03 Y:2014 03 2014 MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT $1,460 $400 Implemented
MZ0156 # 02 Y:2014 02 2014 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,480 $2,000 Implemented
MZ0156 # 01 Y:2014 01 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $23,514 $71,320 Implemented
MZ0141 # 04 Y:2014 04 2014 RECOVER WASTE HEAT FROM EQUIPMENT $4,000 $6,000 Not Implemented
MZ0141 # 08 Y:2014 08 2014 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $3,940 $0 Implemented
MZ0141 # 07 Y:2014 07 2014 INSTALL OCCUPANCY SENSORS $10,446 $1,875 Not Implemented
MZ0141 # 06 Y:2014 06 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $23,518 $21,850 Implemented
MZ0141 # 05 Y:2014 05 2014 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $11,440 $2,500 Not Implemented
AM0660 # 01 Y:2014 01 2014 UTILIZE A LESS EXPENSIVE COOLING METHOD $3,580 $10,000 Not Implemented
MZ0141 # 03 Y:2014 03 2014 RECOVER WASTE HEAT FROM EQUIPMENT $3,254 $11,500 Not Implemented
MZ0141 # 02 Y:2014 02 2014 LOWER CEILING TO REDUCE CONDITIONED SPACE $12,947 $24,000 Not Implemented
MZ0141 # 01 Y:2014 01 2014 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD $2,625 $7,000 Implemented
AM0660 # 10 Y:2014 10 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $115 $135 Not Implemented
AM0660 # 09 Y:2014 09 2014 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $940 $405 Implemented
AM0660 # 08 Y:2014 08 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $955 $660 Implemented
AM0660 # 07 Y:2014 07 2014 USE SYNTHETIC LUBRICANT $1,080 $0 Implemented
AM0660 # 06 Y:2014 06 2014 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,260 $0 Not Implemented
AM0660 # 05 Y:2014 05 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,560 $855 Implemented
AM0660 # 04 Y:2014 04 2014 INSTALL OCCUPANCY SENSORS $1,560 $2,425 Not Implemented
AM0660 # 03 Y:2014 03 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,765 $10 Implemented