Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

20

matching recommendations
Reset
SIC 2086 Bottled And Canned Soft Drinks
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UU0229 # 04 Y:2023 04 2023 USE OPTIMUM TEMPERATURE $2,146 $3,060 Implemented
UU0229 # 03 Y:2023 03 2023 INSTALL HEAT PIPES / RAISE COOLING SETPOINT $4,945 $3,480 Implemented
UU0229 # 02 Y:2023 02 2023 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $11,440 $3,816 Not Implemented
UU0229 # 01 Y:2023 01 2023 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $14,527 $5,600 Implemented
UU0098 # 05 Y:2006 05 2006 OPTIMIZE PLANT POWER FACTOR $2,380 $2,040 Implemented
UU0098 # 04 Y:2006 04 2006 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $410 $2,880 Implemented
UU0098 # 03 Y:2006 03 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,690 $1,000 Implemented
UU0098 # 02 Y:2006 02 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,360 $2,100 Implemented
UU0098 # 01 Y:2006 01 2006 USE DEMAND CONTROLLER OR LOAD SHEDDER $2,060 $0 Implemented
UU0044 # 06 Y:2003 06 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,211 $7,976 Not Implemented
UU0044 # 05 Y:2003 05 2003 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,070 $0 Not Implemented
UU0044 # 04 Y:2003 04 2003 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,476 $800 Implemented
UU0044 # 03 Y:2003 03 2003 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,390 $5,000 Not Implemented
UU0044 # 02 Y:2003 02 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,130 $0 Implemented
UU0044 # 01 Y:2003 01 2003 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,210 $3,508 Not Implemented
UU0034 # 01 Y:2002 01 2002 OPTIMIZE PLANT POWER FACTOR $3,790 $2,000 Not Implemented
UU0034 # 05 Y:2002 05 2002 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,759 $800 Not Implemented
UU0034 # 04 Y:2002 04 2002 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $10,560 $0 Not Implemented
UU0034 # 03 Y:2002 03 2002 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,938 $1,000 Not Implemented
UU0034 # 02 Y:2002 02 2002 INSTALL / REPAIR INSULATION ON STEAM LINES $2,627 $3,621 Not Implemented