Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
532
matching recommendationsSIC | 225 | Knitting Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0242 # 04 Y:1985 | 04 | 1985 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,569 | $0 | Not Implemented |
TN0242 # 05 Y:1985 | 05 | 1985 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $113 | $0 | Not Implemented |
TN0232 # 01 Y:1984 | 01 | 1984 | INSTALL / REPAIR INSULATION ON STEAM LINES | $31,111 | $4,573 | Implemented |
TN0232 # 02 Y:1984 | 02 | 1984 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $11,721 | $18,050 | Not Implemented |
TN0232 # 03 Y:1984 | 03 | 1984 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $14,298 | $0 | Implemented |
TN0232 # 04 Y:1984 | 04 | 1984 | COVER OPEN TANKS | $5,089 | $2,750 | Not Implemented |
TN0232 # 05 Y:1984 | 05 | 1984 | REPAIR AND ELIMINATE STEAM LEAKS | $3,742 | $140 | Implemented |
TN0232 # 06 Y:1984 | 06 | 1984 | INSULATE BARE EQUIPMENT | $2,734 | $855 | Not Implemented |
TN0232 # 07 Y:1984 | 07 | 1984 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $2,670 | $462 | Implemented |
GT0230 # 01 Y:1984 | 01 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $732 | $151 | Implemented |
GT0230 # 02 Y:1984 | 02 | 1984 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $43 | $97 | Implemented |
GT0230 # 03 Y:1984 | 03 | 1984 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $960 | $0 | Not Implemented |
GT0230 # 04 Y:1984 | 04 | 1984 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $1,770 | $1,200 | Not Implemented |
GT0223 # 01 Y:1984 | 01 | 1984 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $8,600 | $16,000 | Not Implemented |
GT0223 # 02 Y:1984 | 02 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,178 | $1,255 | Implemented |
GT0223 # 03 Y:1984 | 03 | 1984 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,548 | $1,441 | Not Implemented |
GT0223 # 04 Y:1984 | 04 | 1984 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $550 | $1,800 | Implemented |
UD0123 # 01 Y:1984 | 01 | 1984 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,488 | $0 | Implemented |
UD0123 # 02 Y:1984 | 02 | 1984 | INSTALL TIMERS AND/OR THERMOSTATS | $3,250 | $3,000 | Not Implemented |
UD0123 # 03 Y:1984 | 03 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,466 | $4,600 | Implemented |
UD0123 # 04 Y:1984 | 04 | 1984 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $347 | $600 | Implemented |
UD0123 # 05 Y:1984 | 05 | 1984 | RECOVER WASTE HEAT FROM EQUIPMENT | $664 | $2,000 | Not Implemented |
TN0170 # 01 Y:1983 | 01 | 1983 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,220 | $15 | Implemented |
TN0170 # 02 Y:1983 | 02 | 1983 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $18,840 | $500 | Implemented |
TN0170 # 03 Y:1983 | 03 | 1983 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,800 | $7,000 | Implemented |