Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
18
matching recommendationsSIC | 239 | Misc. Fabricated Textile Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MO0094 # 06 Y:1993 | 06 | 1993 | USE OPTIMUM TEMPERATURE | $528 | $200 | Implemented |
MO0094 # 05 Y:1993 | 05 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $610 | $690 | Not Implemented |
MO0094 # 04 Y:1993 | 04 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $676 | $1,605 | Not Implemented |
MO0094 # 03 Y:1993 | 03 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,784 | $9,001 | Not Implemented |
MO0094 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,472 | $1,418 | Implemented |
MO0094 # 01 Y:1993 | 01 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,764 | $35,485 | Implemented |
CO0277 # 04 Y:1993 | 04 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $290 | $110 | Not Implemented |
CO0277 # 06 Y:1993 | 06 | 1993 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $420 | $1,000 | Not Implemented |
CO0277 # 05 Y:1993 | 05 | 1993 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $2,420 | $3,600 | Not Implemented |
CO0277 # 03 Y:1993 | 03 | 1993 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $830 | $250 | Not Implemented |
CO0277 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,880 | $580 | Implemented |
CO0277 # 01 Y:1993 | 01 | 1993 | INSTALL TIMERS AND/OR THERMOSTATS | $340 | $150 | Implemented |
TN0488 # 01 Y:1993 | 01 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $636 | $1,060 | Not Implemented |
TN0488 # 06 Y:1993 | 06 | 1993 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,637 | $0 | Implemented |
TN0488 # 05 Y:1993 | 05 | 1993 | USE SYNTHETIC LUBRICANT | $62 | $0 | Implemented |
TN0488 # 04 Y:1993 | 04 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $185 | $510 | Not Implemented |
TN0488 # 03 Y:1993 | 03 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $226 | $358 | Implemented |
TN0488 # 02 Y:1993 | 02 | 1993 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $513 | $0 | Not Implemented |