Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
22
matching recommendationsSIC | 243 | Millwork, Plywood & Structural |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0544 # 01 Y:2000 | 01 | 2000 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $3,310 | $800 | Implemented |
KU0544 # 02 Y:2000 | 02 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,390 | $840 | Implemented |
KU0544 # 03 Y:2000 | 03 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,020 | $920 | Not Implemented |
KU0544 # 04 Y:2000 | 04 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $680 | $280 | Not Implemented |
KU0544 # 05 Y:2000 | 05 | 2000 | INSTALL EQUIPMENT TO MOVE PRODUCT | $31,200 | $2,780 | Implemented |
KU0544 # 06 Y:2000 | 06 | 2000 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $1,020 | $500 | Not Implemented |
MO0277 # 09 Y:2000 | 09 | 2000 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $9,960 | $3,700 | Not Implemented |
MO0277 # 08 Y:2000 | 08 | 2000 | RESCHEDULE BREAKS TO ALLOW FOR CONTINUOUS PRODUCTION | $6,500 | $0 | Not Implemented |
MO0277 # 07 Y:2000 | 07 | 2000 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $690 | $600 | Implemented |
MO0277 # 06 Y:2000 | 06 | 2000 | USE SYNTHETIC LUBRICANT | $488 | $80 | Implemented |
MO0277 # 05 Y:2000 | 05 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $688 | $0 | Implemented |
MO0277 # 04 Y:2000 | 04 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,192 | $200 | Not Implemented |
MO0277 # 03 Y:2000 | 03 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,346 | $439 | Implemented |
MO0277 # 02 Y:2000 | 02 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,970 | $1,937 | Implemented |
MO0277 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $810 | $1,321 | Implemented |
MO0003 # 07 Y:1990 | 07 | 1990 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $248 | $0 | Not Implemented |
MO0003 # 06 Y:1990 | 06 | 1990 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,518 | $100 | Not Implemented |
MO0003 # 05 Y:1990 | 05 | 1990 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,989 | $1,400 | Not Implemented |
MO0003 # 04 Y:1990 | 04 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,542 | $456 | Not Implemented |
MO0003 # 03 Y:1990 | 03 | 1990 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,696 | $2,100 | Not Implemented |
MO0003 # 02 Y:1990 | 02 | 1990 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,851 | $10,420 | Implemented |
MO0003 # 01 Y:1990 | 01 | 1990 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $5,407 | $14,600 | Implemented |