Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
54
matching recommendationsSIC | 243 | Millwork, Plywood & Structural |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UK1609 # 01 Y:2016 | 01 | 2016 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $54,548 | $0 | Not Implemented |
UK1609 # 04 Y:2016 | 04 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $657 | $0 | Implemented |
UK1609 # 03 Y:2016 | 03 | 2016 | INSULATE FEEDWATER TANK | $380 | $140 | Not Implemented |
UK1609 # 02 Y:2016 | 02 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,223 | $3,000 | Implemented |
BS0088 # 03 Y:2016 | 03 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $31,994 | $29,692 | Not Implemented |
BS0088 # 01 Y:2016 | 01 | 2016 | INSTALL / REPAIR INSULATION ON STEAM LINES | $7,541 | $11,782 | Not Implemented |
BS0088 # 02 Y:2016 | 02 | 2016 | LOWER OPERATING PRESSURE OF CONDENSER (STEAM) | $64,374 | $480 | Not Implemented |
BS0080 # 04 Y:2016 | 04 | 2016 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $4,926 | $8,600 | Not Implemented |
BS0080 # 07 Y:2016 | 07 | 2016 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,626 | $8,468 | Not Implemented |
BS0080 # 06 Y:2016 | 06 | 2016 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $264 | $417 | Implemented |
BS0080 # 03 Y:2016 | 03 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $414 | $196 | Not Implemented |
BS0080 # 02 Y:2016 | 02 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,443 | $736 | Implemented |
BS0080 # 01 Y:2016 | 01 | 2016 | TURN OFF EQUIPMENT WHEN NOT IN USE | $15,244 | $1,250 | Implemented |
BS0080 # 05 Y:2016 | 05 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $560 | $500 | Implemented |
UA0163 # 02 Y:2016 | 02 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $18,730 | $500 | Not Implemented |
UA0163 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $54,002 | $184,407 | Not Implemented |
UA0163 # 04 Y:2016 | 04 | 2016 | USE RADIANT HEATER FOR SPOT HEATING | $8,072 | $23,240 | Not Implemented |
UA0163 # 05 Y:2016 | 05 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,032 | $900 | Implemented |
UA0163 # 01 Y:2016 | 01 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $42,679 | $9,795 | Implemented |
UM0464 # 01 Y:2016 | 01 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $361 | $2,000 | Not Implemented |
UM0464 # 04 Y:2016 | 04 | 2016 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $736 | $150 | Implemented |
UM0464 # 02 Y:2016 | 02 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,842 | $5,500 | Not Implemented |
UM0464 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,786 | $3,794 | Implemented |
UM0464 # 05 Y:2016 | 05 | 2016 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $2,107 | $7,900 | Implemented |
UA0156 # 03 Y:2016 | 03 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $30,024 | $6,995 | Not Implemented |