IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

484

matching recommendations
Reset
SIC 2431 Millwork
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0128 # 04 Y:1991 04 1991 RECOVER MECHANICAL ENERGY $15,535 $4,270 Implemented
OR0128 # 05 Y:1991 05 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $545 $0 Implemented
OR0128 # 06 Y:1991 06 1991 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $571 $1,000 Implemented
OR0128 # 07 Y:1991 07 1991 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $88 $189 Implemented
OR0128 # 08 Y:1991 08 1991 OPTIMIZE PLANT POWER FACTOR $308 $750 Implemented
ND0005 # 01 Y:1991 01 1991 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $5,750 $0 Implemented
ND0005 # 02 Y:1991 02 1991 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $80 $200 Implemented
ND0005 # 03 Y:1991 03 1991 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $720 $3,127 Implemented
ND0005 # 04 Y:1991 04 1991 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,663 $6,401 Implemented
ND0005 # 05 Y:1991 05 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $180 $124 Implemented
ND0005 # 06 Y:1991 06 1991 RECOVER WASTE HEAT FROM EQUIPMENT $535 $500 Implemented
ND0005 # 07 Y:1991 07 1991 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $360 $100 Implemented
ND0005 # 08 Y:1991 08 1991 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $78 $0 Implemented
AS0027 # 01 Y:1991 01 1991 REDUCE VENTILATION AIR $4,948 $0 Implemented
AS0027 # 02 Y:1991 02 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $300 $141 Implemented
AS0027 # 03 Y:1991 03 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $820 $3,312 Implemented
AS0027 # 04 Y:1991 04 1991 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $895 $1,200 Implemented
AS0027 # 05 Y:1991 05 1991 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,912 $1,500 Implemented
OR0101 # 02 Y:1990 02 1990 OPTIMIZE PLANT POWER FACTOR $484 $1,050 Implemented
OR0102 # 01 Y:1990 01 1990 OPTIMIZE PLANT POWER FACTOR $925 $1,950 Implemented
OR0103 # 01 Y:1990 01 1990 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $20,739 $26,000 Implemented
OR0103 # 04 Y:1990 04 1990 OPTIMIZE PLANT POWER FACTOR $2,800 $6,000 Implemented
GT0421 # 01 Y:1990 01 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $61 $38 Implemented
GT0421 # 03 Y:1990 03 1990 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $482 $954 Implemented
GT0421 # 06 Y:1990 06 1990 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,820 $500 Implemented