Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,700
matching recommendationsSIC | 25 | Furniture And Fixtures |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0299 # 03 Y:1987 | 03 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,747 | $165 | Implemented |
TN0299 # 04 Y:1987 | 04 | 1987 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $453 | $1,192 | Implemented |
TN0299 # 08 Y:1987 | 08 | 1987 | INSTALL SET-BACK TIMERS | $1,176 | $0 | Implemented |
KU0213 # 01 Y:1987 | 01 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $23,637 | $6,098 | Implemented |
KU0213 # 02 Y:1987 | 02 | 1987 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $7,806 | $9,000 | Implemented |
KU0213 # 03 Y:1987 | 03 | 1987 | INSTALL AUTOMATIC STACK DAMPER | $1,126 | $1,800 | Implemented |
KU0213 # 04 Y:1987 | 04 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,126 | $93 | Implemented |
KU0213 # 05 Y:1987 | 05 | 1987 | INSTALL STORM WINDOWS AND DOORS | $303 | $0 | Implemented |
KU0213 # 07 Y:1987 | 07 | 1987 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $502 | $200 | Implemented |
KU0213 # 09 Y:1987 | 09 | 1987 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $163 | $0 | Implemented |
OK0203 # 01 Y:1986 | 01 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $418 | $41 | Implemented |
OK0203 # 02 Y:1986 | 02 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $227 | $363 | Implemented |
OK0203 # 03 Y:1986 | 03 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $273 | $60 | Implemented |
OK0203 # 04 Y:1986 | 04 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $40 | $55 | Implemented |
UD0202 # 01 Y:1986 | 01 | 1986 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,318 | $0 | Implemented |
UD0202 # 03 Y:1986 | 03 | 1986 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $3,955 | $0 | Implemented |
UD0202 # 04 Y:1986 | 04 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,636 | $791 | Implemented |
UD0202 # 05 Y:1986 | 05 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $1,504 | $80 | Implemented |
KU0197 # 01 Y:1986 | 01 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,730 | $2,554 | Implemented |
KU0197 # 02 Y:1986 | 02 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,331 | $380 | Implemented |
KU0197 # 03 Y:1986 | 03 | 1986 | USE ONLY AMOUNT OF AIR NECESSARY TO PREVENT EXPLOSION HAZARD | $449 | $14 | Implemented |
KU0197 # 04 Y:1986 | 04 | 1986 | INSTALL AUTOMATIC STACK DAMPER | $440 | $700 | Implemented |
KU0197 # 05 Y:1986 | 05 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $170 | $0 | Implemented |
KU0197 # 06 Y:1986 | 06 | 1986 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $225 | $40 | Implemented |
CO0058 # 02 Y:1986 | 02 | 1986 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $1,231 | $1,904 | Implemented |