IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

106

matching recommendations
Reset
SIC 26 Paper And Allied Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IP0162 # 04 Y:2022 04 2022 INSTALL OCCUPANCY SENSORS $377 $137 Implemented
IP0162 # 06 Y:2022 06 2022 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $5,589 $8,000 Not Implemented
IP0162 # 07 Y:2022 07 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $923 $2,186 Implemented
IP0162 # 05 Y:2022 05 2022 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR $45,478 $37,072 Implemented
IP0162 # 03 Y:2022 03 2022 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $634 $152 Implemented
IP0162 # 01 Y:2022 01 2022 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $1,109 $12 Implemented
IP0162 # 02 Y:2022 02 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $8,724 $1,255 Implemented
IP0145 # 05 Y:2021 05 2021 RECOVER WASTE HEAT FROM EQUIPMENT $4,611 $17,283 Not Implemented
IP0145 # 01 Y:2021 01 2021 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $88,444 $27,000 Not Implemented
IP0145 # 02 Y:2021 02 2021 UPGRADE CONTROLS ON COMPRESSORS $24,768 $21,741 Not Implemented
IP0145 # 03 Y:2021 03 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $15,236 $12,797 Not Implemented
IP0145 # 04 Y:2021 04 2021 USE STEAM PRESSURE REDUCTION TO GENERATE POWER $213,186 $665,875 Not Implemented
IP0070 # 03 Y:2016 03 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,137 $40 Implemented
IP0070 # 06 Y:2016 06 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,285 $9,938 Not Implemented
IP0070 # 05 Y:2016 05 2016 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $492 $720 Not Implemented
IP0070 # 02 Y:2016 02 2016 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $8,543 $74 Implemented
IP0070 # 04 Y:2016 04 2016 INSTALL OCCUPANCY SENSORS $996 $113 Implemented
IP0070 # 01 Y:2016 01 2016 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $575 $0 Not Implemented
IP0056 # 01 Y:2016 01 2016 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $1,612 $0 Not Implemented
IP0056 # 07 Y:2016 07 2016 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $356 $170 Not Implemented
IP0056 # 08 Y:2016 08 2016 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $3,273 $2,406 Not Implemented
IP0056 # 09 Y:2016 09 2016 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,909 $1,267 Not Implemented
IP0056 # 10 Y:2016 10 2016 INSTALL OCCUPANCY SENSORS $311 $218 Implemented
IP0056 # 11 Y:2016 11 2016 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $6,064 $6,597 Not Implemented
IP0056 # 12 Y:2016 12 2016 APPLY FOR INVESTMENT INCENTIVES $5,810 $5,000 Not Implemented